PROCTOR, WV —
OSHA Inspection: EAGLE NATRIUM LLC
Referral inspection · Health discipline
At a glance
On , OSHA opened a referral health inspection of EAGLE NATRIUM LLC in 15696 ENERGY ROAD, PROCTOR, WV 26055 (NAICS 325180). OSHA activity number 344837331.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- EAGLE NATRIUM LLC
- Site address
- 15696 ENERGY ROAD
- City
- PROCTOR
- State
- WV
- ZIP
- 26055
- Mailing
- P.O. BOX 191, NEW MARTINSVILLE, WV 26155
What kind of inspection was it?
- Inspection type
- Referral (C)
- Scope
- Partial (B)
- Discipline
- Health
- Advance notice
- No
- Union status
- A
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 325180
- Employees
- 420
- Ownership type
- A
Citations
8 citations on file for this inspection.
1910.119 F01
- Issued
- Oct 28, 2020
- Penalty
- Initial $9,639 · Current $13,494
06401410
General-duty citation text
1910.119(f)(1) The employer did not develop and implement written operating procedures that provide clear instructions for safely conducting activities involved in each covered process consistent with the process safety information and which addresses the applicable elements listed in 29 CFR 1910.119(f)(1)(i) and (f)(1)(ii): (a) 8 Chlorine Circuit: On or about July 12, 2020, per 29 CFR 1910.119(f)(1)(i)(C), Operating procedures did not provide clear instructions as to the location to safely add plane service water to the chlorine production cells during a temporary shutdown. High water pressure could potentially damage the diaphragm and allow hydrogen to mix with the chlorine gas resulting an explosive mixture to form. (b) 8 Chlorine Circuit: On or about July 12, 2020, per 29 CFR 1910.119(f)(1)(i)(C), Operating procedures did not provide clear instructions for correcting a deviation from a low brine level in a cell which can result in arcing and ignition of any chlorine/hydrogen mixtures present. Employees were correcting excessive low brine levels in the cells by hooking up a direct feed line to the cells from the brine header, bypassing the flow control rotometer, which increased the flow rate into the cell up to three times the safe upper flow rate listed in the Safe Operating Envelope Table. (c) 8 Chlorine Circuit: On or about July 12, 2020, per 29 CFR 1910.119(f)(1)(ii), Operating procedures did not provide clear instructions for the 8 Chlorine Circuit that discussed the level of brine in a cell during startup and normal operations which used terms such as sufficient level, unacceptably low, and safe operating level without quantifying or defining these terms to coincide with the process safety information developed. (d) 8 Chlorine Circuit: On or about July 12, 2020, per CFR 1910.119(f)(1)(ii), Operating procedures did not provide clear instructions for the 8 Chlorine Circuit that discussed the level of brine in a cell during startup, normal, and emergency operations which did not list a method measuring the level of anolyte in the cell that coincided with the process safety information developed. The Safe Operating Envelope Table - 1951 listed the safe and normal operating limits for anolyte level in a cell in inches about the top of the top cathode flange however there were no means of measurement available on the cells, such as markings, that coincided with these limits. (e) 8 Chlorine Circuit: On or about July 12, 2020, per CFR 1910.119(f)(1)(i)(D), Operating procedures did not provide clear instructions for emergency shutdown and the conditions requiring emergency shutdown. The level of brine in a cell, as described in company procedures, which would require a shutdown of the circuit was less that the safe lower limit for level listed in the Safe Operating Envelope Table for the process.
Recent events (3)
- — F (S) $13494
- — C (S) $9639
- — Z (S) $9639
1910.119 F01 II B
- Issued
- Oct 28, 2020
- Abate by
- Nov 24, 2020
- Penalty
- Initial $0 · Current $0
06401410
General-duty citation text
29 CFR 1910.119(f)(1)(ii)(B): The employer did not develop and implement written operating procedures that provide clear instructions for steps required to correct or avoid deviation from the operating limits in the covered process. (a) 8 Chlorine Circuit: On or about July 12, 2020 the employer had not developed and implemented written operating procedures that provide clear instructions for correcting a deviation from the listed operating limits. Employees were bypassing the flow control rotometers to correct low levels in the cells by hooking up a feed line directly to the cells from the brine header which increased the flow rate into the cell up to three times the safe upper flow rate listed in the Safe Operating Envelope Table.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1910.119 F01
- Issued
- Oct 28, 2020
- Abate by
- Nov 24, 2020
- Penalty
- Initial $0 · Current $0
06401410
General-duty citation text
29 CFR 1910.119(f)(1)(ii): The employer did not develop and implement written operating procedures that provided clear instructions for safely conducting activities involved in each covered process consistent with the process safety information and which addressed the operating limits: (a) 8 Chlorine Circuit: On or about July 12, 2020 the written operating procedures for the 8 Chlorine Circuit that discussed the level of brine in a cell during startup and normal operations used terms such as sufficient level, unacceptably low, and safe operating level without quantifying these terms to coincide with the process safety information developed. (b) 8 Chlorine Circuit: On or about July 12, 2020 the written operating procedures for the 8 Chlorine Circuit that discussed the level of brine in a cell during startup, normal, and emergency operations did not list a method of measuring the level of anolyte in the cell that coincided with the process safety information developed. The Safe Operating Envelope Table -1951 listed the safe and normal operating limits for anolyte level in a cell in inches above the top of the top cathode flange however there were no means of measurement available on the cells, such as markings, that coincided with these limits.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1910.119 G01 I
- Issued
- Oct 28, 2020
- Abate by
- Nov 24, 2020
- Penalty
- Initial $0 · Current $0
06401410
General-duty citation text
29 CFR 1910.119(g)(1)(i): The employer did not train each employee before being involved in operating a newly assigned process in the operating procedures as specified in paragraph (f) of this section: (a) 8 Chlorine Circuit: On or about July 12, 2020 the employer had not trained employees on the Safe Operating Envelope Tables for the process in that employees were not made aware that the lowest safe operating level of brine in a cell is four inches above the top of the top cathode flange. (b) 8 Chlorine Circuit: On or about July 12, 2020 the employer had not trained employees on the Safe Operating Envelope Tables for the process in that employees were not made aware that the highest safe flow rate of brine into an operating cell is ten gallons per minute.
Recent events (3)
- — F (S) $0
- — C (S) $0
- — Z (S) $0
1910.119 F01 I D
- Issued
- Oct 28, 2020
- Abate by
- Nov 24, 2020
- Penalty
- Initial $13,494 · Current $0 Reduced
06401410
General-duty citation text
29 CFR 1910.119(f)(1)(i)(D): The employer did not develop and implement written operating procedures that provide clear instructions for emergency shutdown, including the conditions under which emergency shutdown is required: (a) 8 Chlorine Circuit: On or about July 12, 2020 the employer had not developed and implemented written operating procedures that provide clear instructions for emergency shutdown and the conditions requiring emergency shutdown. The level of brine in a cell, as described in company procedures, that would require a shut down of the circuit was less than the safe lower limit for level listed in the Safe Operating Envelope Table for the process.
Recent events (3)
- — F (S) $0
- — C (S) $13494
- — Z (S) $13494
1910.119 J02
- Issued
- Oct 28, 2020
- Abate by
- Nov 24, 2020
- Penalty
- Initial $9,639 · Current $9,639
06401410
General-duty citation text
29 CFR 1910.119(j)(2): The employer did not establish and implement written procedures to maintain the on-going integrity of process equipment: (a) No. 8 Chlorine Circuit: On or about July 12, 2020 the employer had not established and implemented a procedure for inspecting and testing the low brine flow alarm (FT-1671) that alerts operators of a hazardous low brine flow to the chlorine production cells.
Recent events (3)
- — F (O) $9639
- — C (S) $9639
- — Z (S) $9639
1910.119 E03 I
- Issued
- Oct 28, 2020
- Abate by
- Nov 24, 2020
- Penalty
- Initial $0 · Current $0
06401410
General-duty citation text
29 CFR 1910.119(e)(3)(i): The process hazard analysis did not address the hazards of the process: (a) 8 Circuit: On or about July 12, 2020 the Process Hazard Analysis for the No. 8 Chlorine Circuit did not address the hazard of using low wavelength light sources which have the potential to initiate an explosive chemical reaction between mixtures of the hydrogen and chlorine gas that can be present in the chlorine production process.
Recent events (3)
- — F (O) $0
- — C (O) $0
- — Z (O) $0
1910.119 F03
- Issued
- Oct 28, 2020
- Abate by
- Nov 24, 2020
- Penalty
- Initial $0 · Current $0
06401410
General-duty citation text
29 CFR 1910.119(f)(3): The employer did not certify annually that operating procedures were current and accurate: (a) 8 Chlorine Circuit: On or about July 12, 2020 the employer had not certified annually that operating procedures were current and accurate in that procedure 444 Bypass or Repair Brine Line to a Cell was last reviewed and certified as accurate on July 12, 2017.
Recent events (3)
- — F (O) $0
- — C (O) $0
- — Z (O) $0
More inspections at Eagle Natrium LLC
View Eagle Natrium LLC's full OSHA safety record →
More inspections in this industry (NAICS 325180)
More inspections in WV