LAKE CITY, PA —
OSHA Inspection: SHIRIN K. MIRZAYEV
Planned inspection · Safety discipline
At a glance
On , OSHA opened a planned safety inspection of SHIRIN K. MIRZAYEV in 2881 MECHANIC STREET, LAKE CITY, PA 16423 (NAICS 238160). OSHA activity number 345014641.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- SHIRIN K. MIRZAYEV
- Site address
- 2881 MECHANIC STREET
- City
- LAKE CITY
- State
- PA
- ZIP
- 16423
- Mailing
- 5843 COURTLAND DRIVE, ERIE, PA 16509
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238160
- Employees
- 6
- Ownership type
- A
Citations
8 citations on file for this inspection.
1910.1200 E01
- Issued
- Dec 10, 2020
- Abate by
- Apr 1, 2021
- Penalty
- Initial $1,908 · Current $1,000 Reduced
0040043009952460
General-duty citation text
29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met and the employer had not developed or implemented a written hazard communication program which at least included the requirements outlined in 29 CFR 1910.1200(e)(1)(i) and (e)(1)(ii): (Construction Reference: 1926.59) A.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees were using chemicals including, but not limited to, Firestone Single-Ply LVOC Bonding Adhesive (W56-358-715L) during roofing operations. The employer did not develop and implement a written hazard communication program. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $1000
- — Z (S) $1908
1910.1200 G08
- Issued
- Dec 10, 2020
- Abate by
- Jan 14, 2021
- Penalty
- Initial $0 · Current $0
0040043009952460
General-duty citation text
29 CFR 1910.1200(g)(8): The employer did not maintain in the workplace copies of the required safety data sheets for each hazardous chemical, and did not ensure that they were readily accessible during each work shift to employees when they were in their work area(s): (Construction Reference: 1926.59) A.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees were using chemicals including, but not limited to, Firestone Single-Ply LVOC Bonding Adhesive (W56-358-715L) during roofing operations. Safety data sheets for the chemicals were not present on-site. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.1200 H01
- Issued
- Dec 10, 2020
- Abate by
- Apr 1, 2021
- Penalty
- Initial $0 · Current $0
0040043009952460
General-duty citation text
29 CFR 1910.1200(h)(1): Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area: (Construction Reference: 1926.59) A.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees were using chemicals including, but not limited to, Firestone Single-Ply LVOC Bonding Adhesive (W56-358-715L) during roofing operations. Employees did not have hazard communication training. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1926.501 B04 I
- Issued
- Dec 10, 2020
- Abate by
- Jan 7, 2021
- Penalty
- Initial $8,906 · Current $4,500 Reduced
General-duty citation text
29 CFR 1926.501(b)(4)(i): Each employee on walking/working surfaces was not protected from falling through holes (including skylights), more than six feet (1.8 m) above lower levels, by personal fall arrest systems, covers, or guardrail systems erected around such holes: A.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees were exposed to fall hazards through roof openings for HVAC units when working at a height of 18.1-feet when performing roofing activities. The openings were not guarded by covers or guardrails. Employees were not utilizing any fall protection systems. Shirin K. Mirzayev dba Super-Roofer was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1926.501(b)(4)(i), which was contained in OSHA inspection number 1189636, citation number 1, item number 2 and was affirmed as a final order on June 30, 2017, with respect to a workplace located at 818-824 State Street, Erie, PA 16501. ABATEMENT CERTIFICATION AND DOCUMENTATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation. This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement. IN ADDITION, abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic, or video evidence or abatement or other written records.
Recent events (2)
- — I (R) $4500
- — Z (R) $8906
1926.501 B10
- Issued
- Dec 10, 2020
- Abate by
- Jan 7, 2021
- Penalty
- Initial $8,906 · Current $4,500 Reduced
General-duty citation text
29 CFR 1926.501(b)(10): Each employee engaged in roofing activities on low-slope roofs with unprotected sides and edges 6 feet or more above lower levels, was not protected from falling by guardrail systems, safety net systems, personal fall arrest systems, or a combination of warning line system and guardrail system, warning line system and safety net system, or warning line system and personal fall arrest system, or warning line system and safety monitoring system. Or, on roofs 50-feet (15.25 m) or less in width, each employee was not protected by use of a monitoring system. A.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees were exposed to fall hazards when working at heights of between 18.1-feet and 20.5-feet on a low-sloped roof when performing roofing activities. Employees were not utilizing any fall protection systems. Shirin K. Mirzayev dba Super-Roofer was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1926.501(b)(10), which was contained in OSHA inspection number 1189636, citation number 1, item number 1-a and was affirmed as a final order on June 30, 2017, with respect to a workplace located at 818-824 State Street, Erie, PA 16501. ABATEMENT CERTIFICATION AND DOCUMENTATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation. This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement. IN ADDITION, abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic, or video evidence or abatement or other written records.
Recent events (2)
- — I (R) $4500
- — Z (R) $8906
1926.21 B02
- Issued
- Dec 10, 2020
- Abate by
- Apr 1, 2021
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.21(b)(2):The employer did not instruct each employee in the recognition and avoidance of unsafe condition(s) and the regulation(s) applicable to his work environment to control or eliminate any hazard(s) or other exposure to illness or injury: A.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees were working with flammable liquids including, but not limited to, Firestone Single-Ply LVOC Bonding Adhesive (W56-358-715L) during roofing operations. The employer had portable dry chemical fire extinguishers on-site. Employees were permitted to use the portable dry chemical fire extinguishers. Employees did not have training on the proper selection and use of portable fire extinguishers. B.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees were provided with personal protective equipment including, but not limited to, Hand Crew nitrile coated gloves. Employees were not provided with personal protective equipment training. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $0
- — Z (O) $0
1926.150 C01 VI
- Issued
- Dec 10, 2020
- Abate by
- Jan 7, 2021
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.150(c)(1)(vi): A fire extinguisher, rated not less than 10B, was not provided within 50 feet of wherever more than 5 gallons of flammable or combustible liquids or 5 pounds of flammable gas were being used on the jobsite: A.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees were using flammable liquids including, but not limited to, Firestone Single-Ply LVOC Bonding Adhesive (W56-358-715L) during roofing operations. A fire extinguisher was not located on the roof of the structure. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $0
- — Z (O) $0
1926.503 B01
- Issued
- Dec 10, 2020
- Abate by
- Apr 1, 2021
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1926.503(b)(1): The employer did not verify fall protection training by preparing a written certification record: A.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: The employer provided fall protection training to employees. The employer did not certify the training with a written certification record. B.) Shirin K. Mirzayev dba Super-Roofer, 2881 Mechanic Street, Lake City, PA 16423, on or about November 4, 2020 and times prior thereto: Employees had fall protection training prior to employment. The employer did not certify the training with a written certification record. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $0
- — Z (O) $0
More inspections at Shirin K. Mirzayev
View Shirin K. Mirzayev's full OSHA safety record →
More inspections in this industry (NAICS 238160)
More inspections in PA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345014641.