OSHA Inspection: ZILY CONSTRUCTION INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of ZILY CONSTRUCTION INC. in 2028 N FREMONT ST, CHICAGO, IL 60614 (NAICS 238140). OSHA activity number 345481295.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Zily Construction INC. — free Get an email when a new federal OSHA severe-injury report for Zily Construction INC. is published. One employer, no account, unsubscribe in one click.
Site address
2028 N FREMONT ST
City
CHICAGO
State
IL
ZIP
60614
Mailing
7146 S OCTAVIA AVE, BRIDGEVIEW, IL 60455
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
2
Ownership type
A

4 citations on file for this inspection.

1926.451 B01

Serious Gravity 10 1 instance 1 exposed
Issued
Sep 13, 2021
Abate by
Sep 23, 2021
Penalty
Initial $4,096 · Current $2,015 Reduced
29 CFR 1926.451(b)(1):  Each platform on all working levels was not fully planked or decked between front uprights and the guardrail supports:     a) On August 17, 2021, employees working from frame scaffolding were exposed to fall hazards of greater than 25 feet where the scaffold platform was not fully decked.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $2015.48
  • — Z (S) $4096

1926.451 G01

Serious Gravity 10 1 instance 1 exposed
Issued
Sep 13, 2021
Abate by
Sep 23, 2021
Penalty
Initial $0 · Current $0
29 CFR 1926.451(g)(1):  Each employee on a scaffold more than 10 feet above a lower level was not protected from falling to that lower level:  a)  On August 17, 2021, employees working from frame scaffolding were exposed to fall hazards of greater than 25 feet.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification.  This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.451 C01

Serious Gravity 5 1 instance 1 exposed
Issued
Sep 13, 2021
Abate by
Sep 23, 2021
Penalty
Initial $2,926 · Current $1,492 Reduced
29 CFR 1926.451(c)(1):  Supported scaffold(s) with a height to base width (including outrigger supports) ratio greater than four to one (4:1) was not restrained from tipping by guying, tying, bracing, or equivalent means:  a)  On August 17, 2021, employees were exposed to fall hazards while working on frame scaffolding exceeding a 4:1 height to base width ratio which was not restrained from tipping by any means.  In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
  • — I (S) $1492.26
  • — Z (S) $2926

1926.451 E01

Serious Gravity 5 1 instance 1 exposed
Issued
Sep 13, 2021
Abate by
Sep 23, 2021
Penalty
Initial $2,926 · Current $1,492 Reduced
29 CFR 1926.451(e)(1):  Portable ladder, hook-on ladder, attachable ladder, stair tower, stairway-type ladder, ramp, runway, integral prefabricated scaffold access, or direct access from another scaffold, structure, personnel hoist, or similar surface was not used to access scaffold platforms more than 2 feet above or below a point of access:   a)  On August 17, 2021, employees were exposed to a fall hazards while accessing and egressing the work platform of a frame scaffold.  In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET).
Recent events (2)
  • — I (S) $1492.26
  • — Z (S) $2926

View Zily Construction INC.'s full OSHA safety record →