OSHA Inspection: NLMK PENNSYLVANIA

Federal Agency inspection · Safety discipline

On , OSHA opened a federal Agency safety inspection of NLMK PENNSYLVANIA in 15 ROEMER BLVD., FARRELL, PA 16121 (NAICS 331110). OSHA activity number 345574313.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Nlmk Pennsylvania — free Get an email when a new federal OSHA severe-injury report for Nlmk Pennsylvania is published. One employer, no account, unsubscribe in one click.
Establishment
NLMK PENNSYLVANIA
Site address
15 ROEMER BLVD.
City
FARRELL
State
PA
ZIP
16121
Mailing
15 ROEMER BLVD., FARRELL, PA 16121
Inspection type
Federal Agency (M)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
331110
Employees
363
Ownership type
A

3 citations on file for this inspection.

1910.22 A01

Serious Gravity 5 2 instances 8 exposed
Issued
Apr 5, 2022
Abate by
Jun 17, 2022
Penalty
Initial $8,287 · Current $7,000 Reduced
29 CFR  1910.22(a)(1):  The employer did not ensure that all places of employment, passageways, storerooms, service rooms, and walking-working surfaces are kept in a clean, orderly, and sanitary condition.   a.)  NLMK Pennsylvania; roll shop - On or about 10/12/21, and at times prior thereto,  the roll shop was congested with rolls, roll racks and other items making it difficult for employees to move in the area and out of the way of crane loads and other equipment.  b.)  NLMK Pennsylvania; roll shop - On or about 10/12/21, and at times prior thereto, the floor of the roll shop was covered in grease and oil.  There were rags and pig mats covering the floor which were also covered in the oil and grease.  ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below).  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $7000
  • — Z (S) $8287

5(a)(1)

Serious Gravity 10 2 instances 8 exposed
Issued
Apr 5, 2022
Abate by
Apr 29, 2022
Penalty
Initial $14,502 · Current $14,502
OSH ACT of 1970 Section (5)(a)(1)  Section 5(a)(1) of the Occupational Safety and Health Act: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees, in that employees  were exposed to struck-by hazards from the stored energy of stuck chocks on a mill rolls that was created  by the chocks being pulled with a crane:  a.)  NLMK Pennsylvania; roll shop - On or about 10/12/21, and at times prior thereto,  a P & H 75 ton crane and chain sling were being utilized to remove a chock assembly from the center of the roll.  The chock assembly came out, struck, and pinned an employee to another roll sitting behind him.  Abatement Note: Among other methods, feasible and acceptable means to correct the hazardous conditions include: 1. Establish procedures that outline danger zones and where employees can stand. 2. Train employees involved or the new procedures and danger zones.  ABATEMENT CERTIFICATION AND DOCUMENTATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation.  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement. IN ADDITION, abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic, or video evidence or abatement or other written records.
Recent events (2)
  • — I (S) $14502
  • — Z (S) $14502

1910.303 G01 II

Other-than-serious Gravity 1 1 instance 8 exposed
Issued
Apr 5, 2022
Abate by
Apr 29, 2022
Penalty
Initial $6,215 · Current $2,000 Reduced
29 CFR  1910.303(g)(1)(ii):The required working space about electric equipment rated 600 volts, nominal, or less to ground, was used for storage:  a.)  NLMK Pennsylvania; storage room off by roll shop - On or about 10/12/21, and at times prior thereto, a trash can, cardboard and a metal pole were stored in front of an electrical panel.   ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below).  This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (O) $2000
  • — Z (S) $6215

View Nlmk Pennsylvania's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345574313.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.