OSHA Inspection: OH CONSTRUCTION, LLC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of OH CONSTRUCTION, LLC in 4912 WISCONSIN AVENUE, NW, WASHINGTON, DC 20016 (NAICS 238130). OSHA activity number 345760508.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch OH Construction, LLC — free Get an email when a new federal OSHA severe-injury report for OH Construction, LLC is published. One employer, no account, unsubscribe in one click.
Site address
4912 WISCONSIN AVENUE, NW
City
WASHINGTON
State
DC
ZIP
20016
Mailing
401 HARDING DRIVE, SILVER SPRING, MD 20901
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Last modified
Data loaded
NAICS code
238130
Employees
5
Ownership type
A

11 citations on file for this inspection.

1926.56 A

Serious Gravity 5 1 instance 5 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $2,735 · Current $2,735
29 CFR  1926.56(a):While work was in progress, construction areas, ramps, runways, corridors, offices, shops or storage areas were not lighted to the minimum illumination intensities as listed in Table D-3 of 29 CFR 1926.56:  a) Stairway Between First and Second - Employees were using stairway that was not provided with lighting, on or about 02/02/2022.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $2735

1926.403 D01

Serious Gravity 1 1 instance 5 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $2,051 · Current $2,051
29 CFR  1926.403(d)(1):Electric equipment was not firmly secured to the surface on which it was mounted:  a) Basement Level - Employees were using a 4 way temporary electrical outlet to supply power to a DeWalt portable electric air compressor where the outlet was not secured but hanging by the BX cable, on or about 02/02/2022.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $2051

1926.403 H

Serious Gravity 1 1 instance 5 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $0 · Current $0
29 CFR  1926.403(h): Each service, feeder, and branch circuit was not legibly marked at its disconnecting means or overcurrent device to indicate its purpose, nor located and arranged so that the purpose was evident:  a) Basement Level -  Circuit breakers in a temporary service panel that were being used to power portable tools were not labeled, on or about 02/02/2022.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $0

1926.404 B01 I

Serious Gravity 1 1 instance 5 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $0 · Current $0
29 CFR  1926.404(b)(1)(i):Employer did not use either ground fault circuit interrupters as specified in paragraph (b)(1)(ii) of this section, or an assured equipment grounding conductor program as specified in paragraph (b)(1)(iii) of this section to protect employees on construction sites:  a) Jobsite - Employees were using temporary electric power to supply portable electric tools and a ground fault circuit interrupter protection was not provided,  on or about 02/02/2022.   In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $0

1926.405 B02

Serious Gravity 5 1 instance 5 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $0 · Current $0
29 CFR  1926.405(b)(2):In an energized installation, each outlet box did not have a cover, faceplate, or fixture canopy:  a) Basement Lower Level - Employees were using a temporary 4-way electric outlet to provide power to a DeWalt portable electric compressor and the cover was missing from the outlet, exposing live electrical parts, on or about 02/02/2022.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $0

1926.701 B

Serious Gravity 5 1 instance 5 exposed
Issued
Aug 1, 2022
Penalty
Initial $3,419 · Current $3,419
29 CFR  1926.701(b):All protruding reinforcing steel, onto and/or into which employees could fall, was not guarded to eliminate the hazard of impalement:  (a) Rear Entrance - A piece of rebar that was 12 inches in height and was 6 inches from the side of a stairway and not covered to prevent an impalement hazard, on or about 02/02/2022.  In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $3419

1926.1052 B02

Serious Gravity 5 1 instance 5 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $2,735 · Current $2,735
29 CFR  1926.1052(b)(2): Foot traffic was not prohibited on skeleton metal stairs where permanent treads and/or landings were to be installed at a later date and the stairs were not fitted with secured temporary treads and/or landings long enough to cover the entire tread or landing area:  a) Stairway Between First and Second Floors - Employees were using skeleton steel stairway to gain access between floors and the pans were not filled-in, on or about 02/02/2022.   In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $2735

1926.1052 C01 I

Serious Gravity 1 1 instance 5 exposed
Issued
Aug 1, 2022
Penalty
Initial $0 · Current $0
29 CFR  1926.1052(c)(1)(i): Stairways having four or more risers or rising more than 30 inches (76 cm), whichever is less, were not equipped with at least one handrail:  a) Rear Entrance - Stairway to gain access to the building was 30 inches in height with a total of 4 risers and was missing a handrail, on or about 02/02/2022.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $0

1926.1053 B01

Serious Gravity 5 1 instance 1 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $2,735 · Current $2,735
29 CFR  1926.1053(b)(1): Where portable ladders were used for access to an upper landing surface and the ladder's length allows, the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface being accessed:  a) Second Floor - Employee was standing on the top step of a 6' portable step ladder to gain access to the top plate and the ladder was 4 feet short of the landing, on or about 02/02/2022.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $2735

1926.1053 B13

Serious Gravity 1 1 instance 1 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $0 · Current $0
29 CFR  1926.1053(b)(13): The top or top step of a stepladder was used as a step:  a) Second Floor - Employee was standing on the top step of a Louisville 6 foot portable step ladder during a framing operation, on or about 02/02/2022.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).
Recent events (1)
  • — Z (S) $0

1926.501 B13

Repeat Gravity 10 1 instance 2 exposed
Issued
Aug 1, 2022
Abate by
Aug 5, 2022
Penalty
Initial $9,571 · Current $9,571
29 CFR  1926.501(b)(13):Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b):  a) Second Floor South Side - Employees were on an exterior top plate during a framing operation and exposed to a 20 foot fall hazard, on or about 02/02/2022.  OH Construction, LLC. was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1926.501(b)(13), which was contained in OSHA inspection number 1305442, citation number 1, item number 2 and was affirmed as a final order on 07/03/2018, with respect to a workplace located at 30016 University Terrace, NW Washington DC 20011.  In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet), in addition, documentation demonstrating the abatement is complete must be included with your certification.  This documentation may include, but is not limited to evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (1)
  • — Z (R) $9571

View OH Construction, LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345760508.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.