Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: MSL CONSTRUCTION INC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of MSL CONSTRUCTION INC in 24 CAROL ANN DRIVE FL 2, ALBANY, NY 12205 (NAICS 238160). OSHA activity number 345989750.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch MSL Construction INC — free Get an email when a new federal OSHA severe-injury report for MSL Construction INC is published. One employer, no account, unsubscribe in one click.
Site address
24 CAROL ANN DRIVE FL 2
City
ALBANY
State
NY
ZIP
12205
Mailing
85 CONGRESS AVE, HOLYOKE, MA 01040
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238160
Employees
10
Ownership type
A

9 citations on file for this inspection.

1903.19 C01

Other-than-serious 7 instances 5 exposed
Issued
Sep 21, 2022
Abate by
Oct 18, 2022
Penalty
Initial $384 · Current $384
29 CFR  1903.19(c)(1):The employer did not certify to OSHA, within 10 calendar days after the abatement date, that each cited violation has been abated:  As of September 13 2022 the Employer had not certified to OSHA that the abatement was completed for the violations from Inspection 15598975, issued on 6/28/2022 with a final order date of 8/19/2022.
Recent events (1)
  • — Z (O) $384

1903.19 D01

Other-than-serious 7 instances 5 exposed
Issued
Sep 21, 2022
Abate by
Oct 18, 2022
Penalty
Initial $384 · Current $384
29 CFR  1903.19(d)(1):The employer did not submit to the Agency documents demonstrating that abatement is complete for any serious violation for which the Agency indicates in the citation that such abatement documentation is required:  As of September 13, 2022, the Employer had not submitted to the Agency the abatement documentation required for the violation issued on 6/28/2022 on which it was indicated that such abatement documentation was required to be submitted to the Agency
Recent events (1)
  • — Z (O) $384

1926.451 G01

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 28, 2022
Abate by
Jul 25, 2022
Penalty
Initial $3,419 · Current $3,419
29 CFR  1926.451(g)(1):Each employee on a scaffold more than 10 feet (3.1 m) above a lower level was not protected from falling to that lower level:  2377 Boston Rd., Wilbraham: On or about May 31, 2022, an employee was observed working from a pump jack scaffold and  was not protected from falling more than 21 feet to the    ground below.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (1)
  • — Z (S) $3419

1926.452 J02

Serious Gravity 5 1 instance 3 exposed
Issued
Jun 28, 2022
Abate by
Jul 25, 2022
Penalty
Initial $3,419 · Current $3,419
29 CFR  1926.452(j)(2): Poles were not  secured to the structure by rigid triangular bracing or equivalent at the bottom, top, and other points as necessary:  2377 Boston Rd., Wilbraham: On or about May 31, 2022, employees were observed working from a pump jack scaffold system that was not connected to the ground at the bottom of the poles.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (1)
  • — Z (S) $3419

1926.454 A

Serious Gravity 5 1 instance 3 exposed
Issued
Jun 28, 2022
Abate by
Jul 25, 2022
Penalty
Initial $3,419 · Current $3,419
29 CFR  1926.454(a): The employer did not  have each employee who performs work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards:  2377 Boston Rd., Wilbraham: On or about May 31, 2022, employees were observed using a scaffold that was improperly erected and contained multiple collapse and fall  hazards and  the employees had not been trained  with regard to the type of  hazards posed by the scaffold being used and to understand the procedures to control or minimize those hazards.   Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (1)
  • — Z (S) $3419

1926.503 A01

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 28, 2022
Abate by
Jul 25, 2022
Penalty
Initial $3,419 · Current $3,419
29 CFR  1926.503(a)(1): The employer did not provide a training program for each employee who might be exposed to fall hazards:  2377 Boston Rd., Wilbraham: On or about May 31, 2022, employee(s) were exposed to fall hazards as part of their assigned duties and the employer had not trained them prior to exposure to these hazards in topics such as but not limited to recognition of fall hazards, dangers of fall hazards and procedures each employee must take to prevent or minimize risk of such exposures.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (1)
  • — Z (S) $3419

1926.503 B01

Serious Gravity 5 1 instance 1 exposed
Issued
Jun 28, 2022
Abate by
Aug 15, 2022
Penalty
Initial $0 · Current $0
29 CFR  1926.503(b)(1):The employer did not verify compliance with paragraph (a) of this section by preparing a written certification record:  2377 Boston Rd., Wilbraham: On or about May 31, 2022,  the employer had not prepared a written certification record of fall protection training which included the name or other identity of the person trained,  the signature of the person trained, date(s) the training was completed and the signature of the person who conducted the training.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (1)
  • — Z (S) $0

1926.1053 B05 I

Serious Gravity 5 3 instances 3 exposed
Issued
Jun 28, 2022
Abate by
Jul 25, 2022
Penalty
Initial $3,419 · Current $3,419
29 CFR  1926.1053(b)(5)(i): Non-self-supporting ladders were not used at an angle such that the horizontal distance from the top support to the foot of the ladder is approximately one-quarter of the working length of the ladder (the distance along the ladder between the foot and the top support):  2377 Boston Rd., Wilbraham: On or about May 31, 2022,  employees were observed using ladders  that were not set at the proper angle and the employer had not ensured that employees using  portable extension ladders to access an upper level were installed in manner in which the working angle did not exceed a ratio of 4:1 or one quarter the working length of the ladder. The ladder was set up at a horizontal distance  greater than 1/4 working length of the ladder,  exposing employees to ladder displacement and fall from height hazards.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (1)
  • — Z (S) $3419

1926.501 B11

Repeat Gravity 5 1 instance 1 exposed
Issued
Jun 28, 2022
Abate by
Jul 25, 2022
Penalty
Initial $6,838 · Current $6,838
29 CFR  1926.501(b)(11):  Each employee on a steep roof with unprotected sides and edges 6 feet (1.8 m) or more above lower levels was not  protected from falling by guardrail systems with toe boards, safety net systems, or personal fall arrest systems:   2377 Boston Rd., Wilbraham: On or about May 31, 2022,  employee(s) were observed performing roofing activities on a steep slope commercial building  with unprotected sides and edges greater than 12 feet to the next lower level and were not protected by either guard rails, safety net systems or personal fall arrest systems exposing them to fall from height hazards.  MSL Construction, Inc was previously cited for a substantially similar violation of this occupational safety and health standard, 29 CFR 1926.501(b)13, which was contained in OSHA inspection number   1563098 , citation number 1, item number 1 and was affirmed as a final order on 3/17/22, with respect to a workplace located at  238 Holyoke St., Ludlow, MA.  Specific abatement documentation that this violation has been corrected must be provided within 10 days of the abatement in accordance with 29 CFR 1903.19(d)(1).
Recent events (1)
  • — Z (R) $6838

View MSL Construction INC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345989750.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.