OSHA Inspection: YAZOO LUMBER & MATS

Unprogrammed Other inspection · Safety discipline

On , OSHA opened an unprogrammed Other safety inspection of YAZOO LUMBER & MATS in 22666 MISSISSIPPI 3, YAZOO CITY, MS 39194 (NAICS 321113). OSHA activity number 346870801.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Yazoo Lumber & Mats — free Get an email when a new federal OSHA severe-injury report for Yazoo Lumber & Mats is published. One employer, no account, unsubscribe in one click.
Establishment
YAZOO LUMBER & MATS
Site address
22666 MISSISSIPPI 3
City
YAZOO CITY
State
MS
ZIP
39194
Mailing
22666 MISSISSIPPI 3, YAZOO CITY, MS 39194
Inspection type
Unprogrammed Other (I)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
321113
Employees
22
Ownership type
A

6 citations on file for this inspection.

1910.303 G01

Other-than-serious Gravity 1 2 instances 3 exposed
Issued
Sep 29, 2023
Abate by
Oct 24, 2023
Penalty
Initial $2,678 · Current $2,500 Reduced
29 CFR  1910.303(g)(1): Sufficient access and working space was not provided and maintained about all electric equipment (operating at 600 volts, nominal, or less to ground) to permit ready and safe operation and maintenance of such equipment:   (a) Maintenance Shop - On or about August 01, 2023, the employer did not ensure there was a 3 feet clearance in front of the electrical panels, exposing the employees to electrical hazards.  (b) File Sharpening Room - On or about August 01, 2023, the employer did not ensure there was a 3 feet clearance in front of the electrical panels, exposing the employees to electrical hazards.
Recent events (2)
  • — I (O) $2500
  • — Z (S) $2678

1910.305 B02

Other-than-serious Gravity 1 1 instance 6 exposed
Issued
Sep 29, 2023
Abate by
Oct 24, 2023
Penalty
Initial $2,678 · Current $2,500 Reduced
29 CFR  1910.305(b)(2): Pull boxes, junction boxes, and fittings were not provided with covers approved for the purpose:    (a)  Mill C - On or about August 1, 2023, electrical panels did not have covers exposing e to electrical hazards.
Recent events (2)
  • — I (O) $2500
  • — Z (S) $2678

1910.212 A

Other-than-serious 2 instances 6 exposed
Issued
Sep 29, 2023
Abate by
Oct 24, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.212(a)(1):  One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks.   (a) Mill C - On or about August 01, 2023, the employer did not provide fixed guarding at the end of the conveyor for the trim saw, exposing employees to a caught by hazard.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.219 C04 I

Other-than-serious 1 instance 22 exposed
Issued
Sep 29, 2023
Abate by
Oct 24, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.219(c)(4)(i): Unguarded shaft end(s) projected more than one half the diameter of the shaft.  (a)  Mill C - On or about August 01, 2023, the employer did not provide guarding for rotating shafts exposing the employees to the hazard of being entangled in moving parts.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.303 B07 I

Other-than-serious 1 instance 6 exposed
Issued
Sep 29, 2023
Abate by
Oct 24, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.303(b)(7)(i): Unused openings in boxes, raceways, auxiliary gutters, cabinets, equipment cases, or housings shall be effectively closed to afford protection substantially equivalent to the wall of the equipment.  (a) Mill C: Control Room - On or about August 01, 2023, the employer did not ensure knockouts were covered, exposing the employees to electrical hazards.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

1910.334 A02 I

Other-than-serious 2 instances 6 exposed
Issued
Sep 29, 2023
Abate by
Oct 24, 2023
Penalty
Initial $0 · Current $0
29 CFR  1910.334(a)(2)(i): Portable cord- and plug connected equipment and flexible cord sets (extension cords) were not visually inspected before use on any shift for external defects (such as loose parts, deformed and missing pins, or damage to outer jacket or insulation) and for evidence for possible internal damage (such as pinched or  crushed outer jacket).  Mill P - On or about August 01, 2023, the employer did not ensure cords attached to fans in the workplace were inspected prior to use, exposing employees to a shock hazard.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View Yazoo Lumber & Mats's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 346870801.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.