Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: PINE CREEK CONSTRUCTION, LLC

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of PINE CREEK CONSTRUCTION, LLC in 47 EAST MAIN STREET, NEW KINGSTOWN, PA 17072 (NAICS 236220). OSHA activity number 347044919.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Pine Creek Construction, LLC — free Get an email when a new federal OSHA severe-injury report for Pine Creek Construction, LLC is published. One employer, no account, unsubscribe in one click.
Site address
47 EAST MAIN STREET
City
NEW KINGSTOWN
State
PA
ZIP
17072
Mailing
6140 STATE ROUTE 225, ELIZABETHVILLE, PA 17023
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
Employees
22
Ownership type
A

3 citations on file for this inspection.

1926.503 C03

Serious Gravity 5 1 instance 2 exposed
Issued
Oct 26, 2023
Abate by
Feb 1, 2024
Penalty
Initial $4,465 · Current $7,500
1926.503(c)(3)  Inadequacies in an affected employee's knowledge or use of fall protection systems or equipment indicate that the employee has not retained the requisite understanding or skill:    a. JLG Scissor Lift - On or about October 19, 2023, employees were observed climbing the guardrail system of the scissor lift (mobile scaffold) while at heights greater than 15 feet above grade.    Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (S) $7500
  • — Z (S) $4465

1926.1051 A

Deleted Serious Gravity 5 1 instance 2 exposed
Issued
Oct 26, 2023
Abate by
Nov 9, 2023
Penalty
Initial $0 · Current $0
29 CFR 1926.1051(a): Stairways or ladders were not provided at all personnel points of access where there was a break in elevation of 19 inches (48 cm) or more, and no ramp, runway, sloped embankment, or personnel hoist was provided:   a. JLG Scissor Lift - On or about October 19, 2023, employees were raising a scissor lift to approximately 20 feet above grade and then climbing the rail system to gain access to the trusses where they were walking the trusses to install supports.   Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1926.501 B01

Deleted Serious Gravity 10 1 instance 2 exposed
Issued
Oct 26, 2023
Abate by
Nov 9, 2023
Penalty
Initial $6,250 · Current $0 Reduced
29 CFR 1926.501(b)(1): Each employee on a walking/working surface having an unprotected side or edge which was six or more feet (1.8m) or more above a lower level was not protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest system.  a. Trusses - On or about October 19, 2023, employees were observed working between the trusses greater than 20 feet above grade without fall protection. The employees were bracing the trusses by climbing between the trusses with 2x4's to nail into place to serve as bracing.   Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $6250

View Pine Creek Construction, LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 347044919.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.