OSHA Inspection: TEMPCO ELECTRIC HEATER CORPORATION

Referral inspection · Safety discipline

On , OSHA opened a referral safety inspection of TEMPCO ELECTRIC HEATER CORPORATION in 607 N. CENTRAL AVE., WOOD DALE, IL 60191 (NAICS 333414). OSHA activity number 347123366.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Tempco Electric Heater Corporation — free Get an email when a new federal OSHA severe-injury report for Tempco Electric Heater Corporation is published. One employer, no account, unsubscribe in one click.
Site address
607 N. CENTRAL AVE.
City
WOOD DALE
State
IL
ZIP
60191
Mailing
607 N. CENTRAL AVE., WOOD DALE, IL 60191
Inspection type
Referral (C)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
333414
Employees
420
Ownership type
A

4 citations on file for this inspection.

1910.147 C04 II

Serious Gravity 10 1 instance 5 exposed
Issued
Apr 26, 2024
Abate by
Sep 30, 2024
Penalty
Initial $16,131 · Current $9,500 Reduced
29 CFR  1910.147(c)(4)(ii): The procedures shall clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, and the means to enforce compliance including, but not limited to Items A-D of this section:   On or about November 15, 2023, the employer failed to clearly identify all of the specific steps to be followed by employees to isolate and disable the components of the Castec manufactured High-Speed Continuous Sand Mixer, model Celecta-Flo CEL-100, in order to safely de-energize the equipment and control the hazardous electrical energy. The specific machine's energy control procedure lacked specific steps to render safe hazardous residual energy of the spinning auger blade prior to mixer blade access. Additionally, clear and specific verification steps were not prescribed to determine the effectiveness of the energy control measures. The procedure did not contain the required specific information for use by non-maintenance personnel assigned service and maintenance activities such as, but not limited to, cleaning activities. As a result, employees' upper extremities were exposed to caught-in and amputation hazards associated with the equipment's spinning auger blade when performing service and maintenance activities such as, but not limited to, cleaning activities.    Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).
Recent events (2)
  • — I (S) $9500
  • — Z (S) $16131

1910.147 D

Serious Gravity 10 1 instance 2 exposed
Issued
Apr 26, 2024
Abate by
Sep 30, 2024
Penalty
Initial $16,131 · Current $0 Reduced
29 CFR 1910.147(d): Application of control. The established procedures for the application of energy control (the lockout or tagout procedures) shall cover the following elements and actions and shall be done in the following sequence:  On or about November 15, 2023, the employer did not ensure that employees implemented energy control application steps prior to allowing them to perform service and maintenance activities on the Castec manufactured High-Speed Continuous Sand Mixer, model Celecta-Flo CEL-100.  Employees were exposed to caught-in and amputation hazards associated with the unexpected energization and residual energy  of the machine's spinning auger blade during service and maintenance activities, including, but not limited to, cleaning.  As a result, the remaining applicable energy control elements, involving machine isolation [(d)(3)], LOTO device application [(d)(4)], dissipation of residual energy [(d)(5)(i)], and verification of isolation [(d)(6)], were not implemented to protect employees from machine servicing hazards.  Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).
Recent events (2)
  • — I (S) $0
  • — Z (S) $16131

1910.147 C06 I

Serious Gravity 5 1 instance 5 exposed
Issued
Apr 26, 2024
Abate by
Sep 30, 2024
Penalty
Initial $11,524 · Current $9,500 Reduced
29 CFR  1910.147(c)(6)(i): The employer shall conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirements of this standard are being followed.  On or about November 15, 2023, the employer  failed to conduct periodic inspections of the energy control procedure for the Castec manufactured High-Speed Continuous Sand Mixer, model Celecta-Flo CEL-100, at least annually to ensure that the requirements of the lockout/tagout standard were met.  The employer's machine specific energy control procedure contained several deficiencies such as, but not limited to, specific steps to render safe residual energy of the spinning auger blade and specific verification steps to determine the effectiveness of the energy control measures. Employees performing service and maintenance activities on the specific machine were exposed to hazards such as, but not limited to, amputation hazards associated with the spinning auger blade when performing activities such as, but not limited to, cleaning.   Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).
Recent events (2)
  • — I (S) $9500
  • — Z (S) $11524

1910.147 C07 I A

Serious Gravity 10 1 instance 5 exposed
Issued
Apr 26, 2024
Abate by
Sep 30, 2024
Penalty
Initial $16,131 · Current $9,500 Reduced
29 CFR  1910.147(c)(7)(i)(A): Each authorized employee shall receive training in the recognition of applicable hazardous energy sources, the type and magnitude of the energy available in the workplace, and the methods and means necessary for energy isolation and control.  On or about November 15, 2023, the employer failed to ensure that each authorized employee received training in the recognition of applicable hazardous energy sources, the type and magnitude of the energy available in the workplace, and the methods and means necessary for energy isolation and control. Employees were exposed to caught-in and amputation hazards associated with the unexpected energization of the spinning auger blade of the Castec manufactured High-Speed Continuous Sand Mixer, model Celecta-Flo CEL-100 when performing service and maintenance activities such as, but not limited to, cleaning.    Abatement documentation is required for this item in accordance with the requirements of 29 CFR 1903.19(d).
Recent events (2)
  • — I (S) $9500
  • — Z (S) $16131

View Tempco Electric Heater Corporation's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 347123366.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.