OSHA Inspection: RPM CONSTRUCTION

Planned inspection · Health discipline

On , OSHA opened a planned health inspection of RPM CONSTRUCTION in TALO VERDE ESTATES, TRACT 13105, LOT 17, TAMUNING, GU 96931 (NAICS 238110). OSHA activity number 331100743.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch RPM Construction — free Get an email when a new federal OSHA severe-injury report for RPM Construction is published. One employer, no account, unsubscribe in one click.
Establishment
RPM CONSTRUCTION
Site address
TALO VERDE ESTATES, TRACT 13105, LOT 17
City
TAMUNING
State
GU
ZIP
96931
Mailing
PO BOX 315668, TAMUNING, GU 96931
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Health
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238110
Employees
7
Ownership type
A

5 citations on file for this inspection.

1926.50 C

Serious Gravity 1 1 instance 1 exposed
Issued
Apr 27, 2012
Abate by
May 4, 2012
Penalty
Initial $1,800 · Current $300 Reduced
29 CFR 1926.50(c):     A person who has a valid certificate in first-aid training was not available at the worksite to render first-aid:    Talo Verde Estates, tract 13105 lot 17: : On or about 06 DEC 11 and at times prior thereto, workers constructing a new home were 10-20 minutes away from the nearest hospital. Nobody had a valid certificate in first-aid training to render treatment in the event of a fall or injury on the job site.
Recent events (2)
  • — I (S) $300
  • — Z (S) $1800

1910.1200 E01

Serious Gravity 1 1 instance 1 exposed
Issued
Apr 27, 2012
Abate by
May 4, 2012
Penalty
Initial $1,800 · Current $300 Reduced
29 CFR 1910.1200(e)(1):     Employer had not developed or implemented a written hazard communication program which at included the requirements outlined in 29 CFR 1910.1200(e)(1)(i) and (e)(1)(ii): (Construction Reference: 1926.59)      Talo Verde Estates, tract 13105 lot 17: On or about 06 DEC 11 and at times prior thereto, a written hazard communication program was not generated for hazardous materials such as, but not limited to Portland cement, Rustoleum spray paint cans and Customer Blend Cement among other hazardous materials.
Recent events (2)
  • — I (S) $300
  • — Z (S) $1800

1910.1200 E01 I

Serious Gravity 1 1 instance 2 exposed
Issued
Apr 27, 2012
Abate by
May 4, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(e)(1)(i):     The written hazard communication program did not include a list of the hazardous chemicals known to be present using an identity that was referenced on the appropriate material safety data sheet: (Construction Reference: 1926.59)    Talo Verde Estates, tract 13105 lot 17: On or about 06 DEC 11 and at times prior thereto, the inventory list was not generated for hazardous materials such as, but not limited to  Portland cement, Rustoleum spray paint cans and Customer Blend Cement among other hazardous materials.      Note: the list must account for all the hazardous materials used onsite and the material safety data sheets (MSDS).
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.1200 G01

Serious Gravity 1 1 instance 2 exposed
Issued
Apr 27, 2012
Abate by
May 4, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(g)(1):     The employer did not have a material safety data sheet for each hazardous chemical which they used: (Construction Reference: 1926.59)    Talo Verde Estates, tract 13105 lot 17: On or about 06 DEC 11 and at times prior thereto, material safety data sheet were not readily available for hazardous materials such as, but not limited to Portland cement, Rustoleum spray paint cans and Customer Blend Cement among other hazardous materials.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.1200 H01

Serious Gravity 1 1 instance 2 exposed
Issued
Apr 27, 2012
Abate by
May 4, 2012
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(h)(1):     Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area: (Construction Reference: 1926.59)    Talo Verde Estates, tract 13105 lot 17: On or about 06 DEC 11 and at times prior thereto, information and training was not provided for hazardous materials such as, but not limited to Portland cement, Rustoleum spray paint cans and Customer Blend Cement among other hazardous materials.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

View RPM Construction's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 331100743.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.