Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: LM CONSTRUCTION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of LM CONSTRUCTION in 67791 MALL ROAD, SAINT CLAIRSVILLE, OH 43950 (NAICS 236220). OSHA activity number 335178398.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch LM Construction — free Get an email when a new federal OSHA severe-injury report for LM Construction is published. One employer, no account, unsubscribe in one click.
Establishment
LM CONSTRUCTION
Site address
67791 MALL ROAD
City
SAINT CLAIRSVILLE
State
OH
ZIP
43950
Mailing
67682 CLARKE ROAD, SAINT CLAIRSVILLE, OH 43950
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236220
Employees
77
Ownership type
A

5 citations on file for this inspection.

1926.451 B01

Serious Gravity 10 1 instance 4 exposed
Issued
Aug 2, 2012
Abate by
Aug 9, 2012
Penalty
Initial $4,900 · Current $1,715 Reduced
29 CFR 1926.451(b)(1):     Each platform on all working levels of scaffolds shall be fully planked or decked between the front uprights and the guardrail supports.    a. On the south side of the building where employees were applying the Exterior Insulation and Finish Systems (EIFS), the scaffold was not fully planked between the platform and the uprights, thereby exposing employees to a fall hazard.
Recent events (3)
  • — F (S) $1715
  • — C (S) $4900
  • — Z (S) $4900

1926.451 E01

Serious Gravity 5 1 instance 4 exposed
Issued
Aug 2, 2012
Abate by
Aug 9, 2012
Penalty
Initial $3,500 · Current $1,225 Reduced
29 CFR 1926.451(e)(1):     When scaffold platforms are more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from another scaffold, structure, personnel hoist, or similar surface shall be used. Crossbraces shall not be used as a means of access.    a. On the south side of the building where employees were applying Exterior Insulation and Finish Systems (EIFS), the employer failed to provide a safe access to the working level of the scaffold, thereby exposing employees to a fall hazard.
Recent events (3)
  • — F (S) $1225
  • — C (S) $3500
  • — Z (S) $3500

1926.451 F03

Serious Gravity 10 1 instance 4 exposed
Issued
Aug 2, 2012
Abate by
Aug 9, 2012
Penalty
Initial $4,900 · Current $1,715 Reduced
29 CFR 1926.451(f)(3):     Scaffolds and scaffold components shall be inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity.    a. On the south side of the building where employees were applying Exterior Insulation and Finish Systems (EIFS) from a two level scaffold, daily inspections of the scaffold were not performed before each shift, thereby exposing employees to a fall hazard.
Recent events (3)
  • — F (S) $1715
  • — C (S) $4900
  • — Z (S) $4900

1926.451 G04 I

Serious Gravity 5 1 instance 4 exposed
Issued
Aug 2, 2012
Abate by
Aug 9, 2012
Penalty
Initial $3,500 · Current $1,225 Reduced
29 CFR 1926.451(g)(4)(i):     Guardrail systems shall be installed along all open sides and ends of platforms. Guardrail systems shall be installed before the scaffold is released for use by employees other than erection/dismantling crews.    a. On the south side of the building where employees were applying Exterior Insulation and Finish Systems (EIFS), there were no guardrails installed on the scaffold where employees were working at levels above 10 feet, thereby exposing employees to a fall hazard.
Recent events (3)
  • — F (S) $1225
  • — C (S) $3500
  • — Z (S) $3500

1926.502 B01

Serious Gravity 5 1 instance 4 exposed
Issued
Aug 2, 2012
Abate by
Aug 9, 2012
Penalty
Initial $3,500 · Current $1,225 Reduced
29 CFR 1926.502(b)(1):     Top edge height of top rails, or equivalent guardrail system members, shall be 42 inches (1.1 m) plus or minus 3 inches (8 cm) above the walking/working level. When conditions warrant, the height of the top edge may exceed the 45-inch height, provided the guardrail system meets all other criteria of this paragraph.  Note: When employees are using stilts, the top edge height of the top rail, or equivalent member, shall be increased an amount equal to the height of the stilts.    a. On the south side of the building where employees were applying Exterior Insulation and Finish Systems (EIFS), the top guardrail cable on the addition roof was 35 inches or lower, thereby exposing employees to a fall hazard.
Recent events (3)
  • — F (S) $1225
  • — C (S) $3500
  • — Z (S) $3500

View LM Construction's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 335178398.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.