Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: IS ENTERPRISES, INC.

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of IS ENTERPRISES, INC. in 451 S STREET, NW, WASHINGTON, DC 20001 (NAICS 236118). OSHA activity number 339128365.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch IS Enterprises, INC. — free Get an email when a new federal OSHA severe-injury report for IS Enterprises, INC. is published. One employer, no account, unsubscribe in one click.
Site address
451 S STREET, NW
City
WASHINGTON
State
DC
ZIP
20001
Mailing
1324 H STREET, NE, WASHINGTON, DC 20002
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
236118
Employees
6
Ownership type
A

5 citations on file for this inspection.

1926.451 B01

Serious Gravity 5 1 instance 2 exposed
Issued
Jul 12, 2013
Abate by
Jul 18, 2013
Penalty
Initial $2,000 · Current $1,000 Reduced
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii):     a) West Side of the Building - A foreman and a laborer were observed on a tubular welded frame scaffold which was not fully decked exposing them to a 26 foot fall hazard, on or about 06/20/13.     Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $1000
  • — Z (S) $2000

1926.451 E01

Serious Gravity 5 1 instance 2 exposed
Issued
Jul 12, 2013
Abate by
Jul 18, 2013
Penalty
Initial $2,000 · Current $1,000 Reduced
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used.  Cross braces were used as a means of access.     a) West Side of the Building - A foreman and a laborer were observed on a tubular welded frame scaffold which was not fully equipped with an access ladder exposing them to a 26 foot fall hazard, on or about 06/20/13.     Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $1000
  • — Z (S) $2000

1926.451 G01

Serious Gravity 5 1 instance 2 exposed
Issued
Jul 12, 2013
Abate by
Jul 18, 2013
Penalty
Initial $2,000 · Current $1,000 Reduced
29 CFR 1926.451(g)(1): Employees on scaffolds more than 10 feet (3.1 m) above a lower level were not protected from falling to that lower level by fall protection established in paragraphs (g)(1)(i)-(vii) of this section:     a) West Side of the Building - A foreman and a laborer were observed on a tubular welded frame scaffold which was not fully equipped with guardrails exposing them to a 26 foot fall hazard, on or about 06/20/13.     Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $1000
  • — Z (S) $2000

1926.501 B13

Serious Gravity 5 1 instance 2 exposed
Issued
Jul 12, 2013
Abate by
Jul 18, 2013
Penalty
Initial $2,000 · Current $1,000 Reduced
29 CFR 1926.501(b)(13): Each employee(s) engaged in residential construction activities 6 feet (1.8 m) or more above lower levels were not protected by guardrail systems, safety net system, or personal fall arrest system, nor were employee(s) provided with an alternative fall protection measure under another provision of paragraph 1926.501 (b):       a) West Side of the Building - A foreman and laborers were observed using a ramp without guardrails which was placed over top of the basement stairwell exposing them to a 9 foot fall hazard, on or about 06/20/13.     Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
  • — I (S) $1000
  • — Z (S) $2000

1926.100 A

Repeat Gravity 1 1 instance 2 exposed
Issued
Jul 12, 2013
Abate by
Jul 18, 2013
Penalty
Initial $2,400 · Current $2,400
29 CFR 1926.100(a): Employees working in areas where there is a possible danger of head injury from impact, or from falling or flying objects, or from electrical shock and burns, shall be protected by protective helmets.   a) West Side of the Building - A foreman and a laborer were observed without head protection while on a tubular welded frame scaffold and working above each other exposing them to a potential head injury, on or about 06/20/13.   The IS Enterprises, Inc. was previously cited for a violation of this occupational safety and health standard or its equivalent standard 1926.100(a), which was contained in OSHA inspection number 314924531, citation number 1, item number 1c and was affirmed as a final order on 11/22/2010, with respect to a workplace located at 2839 Myrtle Ave N.E., Washington DC, 20018.   Abatement certification and documentation required within 10 days after abatement date. The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement. Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (R) $2400
  • — Z (R) $2400

View IS Enterprises, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 339128365.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.