OSHA Inspection: OAK HILL VENEER, INCORPORATED

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of OAK HILL VENEER, INCORPORATED in 23189 S.R. 14 NORTH P.O. BOX 304, TROY, PA 16947 (NAICS 321211). OSHA activity number 340424845.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch OAK Hill Veneer, Incorporated — free Get an email when a new federal OSHA severe-injury report for OAK Hill Veneer, Incorporated is published. One employer, no account, unsubscribe in one click.
Site address
23189 S.R. 14 NORTH P.O. BOX 304
City
TROY
State
PA
ZIP
16947
Mailing
23189 S.R. 14 NORTH P.O. BOX 304, TROY, PA 16947
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
321211
Employees
55
Ownership type
A

8 citations on file for this inspection.

1910.184 C02

Serious Gravity 1 1 instance 6 exposed
Issued
Jun 24, 2015
Abate by
Jul 21, 2015
Penalty
Initial $2,100 · Current $2,000 Reduced
29 CFR 1910.184(c)(2): Makeshift device(s), knot(s) or bolt(s) were used to shorten sling(s)    a) Half-Round Area, 23189 S.R. 14N, P.O. Box 304, Troy, PA - Employees used a double-bridle sling to lift logs that had a makeshift shortened leg, created by placing a hook on a lifting attachment through a link of an alloy steel chain. Employees were exposed to struck-by hazards due to the unknown rated capacity of the sling, as observed on or about February 25, 2015.    In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation.
Recent events (2)
  • — I (S) $2000
  • — Z (S) $2100

1910.184 E01

Serious Gravity 1 1 instance 6 exposed
Issued
Jun 24, 2015
Abate by
Jul 21, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.184(e)(1): Alloy steel sling(s) did not have permanently affixed durable identification stating size, grade, rated capacity, and reach:  a) Slicer Area, 23189 S.R. 14N, P.O. Box 304, Troy, PA: Employees used a double-bridle sling daily to lift logs with alloy steel chains that lacked permanently affixed durable identification (stating size, grade and rated capacity). Employees were exposed to struck-by hazards due to the unknown rated capacity of the sling, as observed on or about February 25, 2015.  In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.184 E03 I

Serious Gravity 1 1 instance 6 exposed
Issued
Jun 24, 2015
Abate by
Jul 21, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.184(e)(3)(i): A thorough periodic inspection of alloy steel chain slings was not made on a regular basis and/or were done at intervals greater than once every 12 months:  a) Slicer Area, 23189 S.R. 14N, P.O. Box 304, Troy, PA: Employees used a double-bridle sling daily to lift logs with sling components that were not regularly or periodically inspected for damage. Employees were exposed to struck-by hazards created by possible damage going undetected, as observed on or about February 25, 2015.  In accordance with 29 CFR 1903.19(c), abatement certification is required for this violation.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.303 B02

Deleted Serious Gravity 5 1 instance 8 exposed
Issued
Jun 24, 2015
Penalty
Initial $2,800 · Current $0 Reduced
29 CFR 1910.303(b)(2): Listed or labeled electrical equipment was not used or installed in accordance with instructions included in the listing or labeling:  a) Log Prep Area, 501 West Main Street, Plymouth, PA - An extension cord provided power to a steam heater that was used daily, exposing employees to a potential electrical hazard, as observed on or about February 25, 2015.  In accordance with 29 CFR 1903.19(c), abatement certification is not required for this violation. The hazardous condition was corrected during the inspection.
Recent events (2)
  • — I (S) $0
  • — Z (S) $2800

1910.305 G01 IV A

Deleted Serious Gravity 5 1 instance 8 exposed
Issued
Jun 24, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure:  a) Log Prep Area, 501 West Main Street, Plymouth, PA - An extension cord provided power to a steam heater that was used daily, exposing employees to a potential electrical hazard, as observed on or about February 25, 2015.  In accordance with 29 CFR 1903.19(c), abatement certification is not required for this violation. The hazardous condition was corrected during the inspection.
Recent events (2)
  • — I (S) $0
  • — Z (S) $0

1910.212 A01

Repeat Gravity 5 1 instance 6 exposed
Issued
Jun 24, 2015
Penalty
Initial $7,000 · Current $4,000 Reduced
29 CFR 1910.212(a)(1): One or more methods of machine guarding was not provided to protect the operator and other employees in the machine area from hazards such as those created by point of operation, ingoing nip points, rotating parts, flying chips and sparks:    a) Debarking Area, 23189 S.R. 14N, P.O. Box 304, Troy, PA - There were no means to restrict access to employees that worked and walked adjacent to the rotating parts of the HMC debarker. Employees were exposed to caught-in hazards, on or about February 25, 1015.    In accordance with 29 CFR 1903.19(c), abatement certification is not required for this violation. The hazardous condition was corrected during the inspection.    Oak Hill Veneer, Incorporated was previously cited for a violation of this occupational safety and health standard which was contained in OSHA Inspection Number314164146, Citation Number 1, Item Number 5 issued on August 24, 2011, and was affirmed as a Final Order on September 21, 2011, with respect to the workplace located at 23189 S.R. 14N, P.O. Box 304, Troy, PA.
Recent events (2)
  • — I (R) $4000
  • — Z (R) $7000

1910.242 B

Repeat Gravity 1 1 instance 2 exposed
Issued
Jun 24, 2015
Penalty
Initial $10,500 · Current $8,400 Reduced
29 CFR 1910.242(b): Compressed air used for cleaning purposes was not reduced to less than 30 p.s.i.:    a) Log Prep Area, 23189 S.R. 14N, P.O. Box 304, Troy, PA - Employees used compressed air at 65 p.s.i. to clean wood chips from work areas and machines. Employees were exposed to struck-by hazards caused by high pressure air, as observed on or about February 25, 2015.    In accordance with 29 CFR 1903.19(c), abatement certification is not required for this violation. The hazardous condition was corrected during the inspection.    Oak Hill Veneer, Incorporated was previously cited for a repeat violation of this occupational safety and health standard or its equivalent standard, 1910.242(b) which was contained in OSHA Inspection Number 618059, Citation Number 1, Item Number 1 issued on November 13, 2012 and was affirmed as a Final Order on December 20, 2012, with respect to the workplace located at 23189 S.R. 14N, P.O. Box 304, Troy, PA.    Oak Hill Veneer, Incorporated was previously cited for a violation of this occupational safety and health standard or its equivalent standard, 1910.242(b) which was contained in OSHA Inspection Number 314164146, Citation Number 1, Item Number 8 issued on August 24, 2011 and was affirmed as a Final Order on September 21, 2011, with respect to the workplace located at 23189 S.R. 14N, P.O. Box 304, Troy, PA.
Recent events (2)
  • — I (R) $8400
  • — Z (R) $10500

1910.157 C01

Other-than-serious 2 instances 55 exposed
Issued
Jun 24, 2015
Penalty
Initial $0 · Current $0
29 CFR 1910.157(c)(1): Portable fire extinguishers were not mounted, located and identified so that they were readily accessible without subjecting the employees to injuries:  a) Log Prep Area, 23189 S.R. 14N, P.O. Box 304, Troy, PA - An Ansul ABC dry chemical fire extinguisher provided for employee use to fight fires was placed on the floor and not mounted at its identified location. Employees looking to fight incipient stage fires in the area were exposed to the slip, trip, and fall hazards and to the hazards associated with fires and explosions, on or about February 25, 2015.  a) Slicer Area, 23189 S.R. 14N, P.O. Box 304, Troy, PA - An Ansul carbon dioxide fire extinguisher provided for employee use to fight fires was placed underneath a desk and not mounted at its identified location. Employees looking to fight incipient stage fires in the area were exposed to the hazards associated with fires and explosions, on or about February 25, 2015.  In accordance with 29 CFR 1903.19(c), abatement certification is not required for this violation. The hazardous conditions were corrected during the inspection.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View OAK Hill Veneer, Incorporated's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 340424845.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.