Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: J P CONSTRUCTION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of J P CONSTRUCTION in 10730 OKTOC ROAD, STARKVILLE, MS 39759 (NAICS 238140). OSHA activity number 341366938.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch J P Construction — free Get an email when a new federal OSHA severe-injury report for J P Construction is published. One employer, no account, unsubscribe in one click.
Establishment
J P CONSTRUCTION
Site address
10730 OKTOC ROAD
City
STARKVILLE
State
MS
ZIP
39759
Mailing
143 SHAW CIRCLE, COLLINSVILLE, AL 35961
Inspection type
Planned (H)
Scope
Complete (A)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
6
Ownership type
A

8 citations on file for this inspection.

1926.95 A

Serious Gravity 5 1 instance 1 exposed
Issued
Apr 28, 2016
Penalty
Initial $2,000 · Current $2,000
29 CFR 1926.95(a): "Application." Protective equipment, including personal protective equipment for eyes, face, head, and extremities, protective clothing, respiratory devices, and protective shields and barriers, shall be provided, used, and maintained in a sanitary and reliable condition wherever it is necessary by reason of hazards of processes or environment, chemical hazards, radiological hazards, or mechanical irritants encountered in a manner capable of causing injury or impairment in the function of any part of the body through absorption, inhalation or physical contact.    (a) Building No. 3 - On or about March 30, 2016 employee was exposed to a chemical hazard while applying diluted Muriatic acid to an exterior brick wall. The employee was not using PPE, such as and not limited to, protective eye goggles, gloves and protective clothing.
Recent events (3)
  • — A (S) $2000
  • — I (S) $1160
  • — Z (S) $2000

1926.451 B01

Serious Gravity 10 1 instance 1 exposed
Issued
Apr 28, 2016
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.451(b)(1): Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports as specified in paragraphs 1926.451(b)(1)(i)-(ii)    (a) Building No. 3 - On or about March 30, 2016 employee was cleaning an exterior brick wall while working from scaffolding that was not fully planked.    - East Side.  One bay scaffolding. 7 feet wide x 30 feet high (5 sections high)     - North side. Two bay scaffolding. 14 feet wide x 30 feet high (5 sections high)  - West Side. One bay scaffolding. 7 feet wide x 30 feet (5 sections high)
Recent events (3)
  • — A (S) $2800
  • — I (S) $1635
  • — Z (S) $2800

1926.451 C01 II

Serious Gravity 10 1 instance 1 exposed
Issued
Apr 28, 2016
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.451(c)(1)(ii):  Guys, ties, and braces shall be installed according to the scaffold manufacturer's recommendations or at the closest horizontal member to the 4:1 height and be repeated vertically at locations of horizontal members every 20 feet (6.1 m) or less thereafter for scaffolds 3 feet (0.91 m) wide or less, and every 26 feet (7.9 m) or less thereafter for scaffolds greater than 3 feet (0.91 m) wide. The top guy, tie or brace of completed scaffolds shall be placed no further than the 4:1 height from the top. Such guys, ties and braces shall be installed at each end of the scaffold and at horizontal intervals not to exceed 30 feet (9.1 m) (measured from one end [not both] towards the other).    (a) Building No. 3 - On or about March 30, 2016 employee was cleaning an exterior bricks wall while working from scaffolding that was not secured to the structure.    - East Side. One bay scaffolding. 7 feet wide x 5 feet deep x 30 feet high (5 sections high)     - North side. Two bay scaffolding. 14 feet wide x 5 feet deep x 30 feet high (5 sections high)  - West Side. One bay scaffolding. 7 feet wide x 5 feet deep x 30 feet (5 sections high)
Recent events (3)
  • — A (S) $2800
  • — I (S) $1635
  • — Z (S) $2800

1926.451 E01

Serious Gravity 10 1 instance 1 exposed
Issued
Apr 28, 2016
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.451(e)(1): scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from another scaffold, structure, personnel hoist, or similar surface shall be used. Crossbraces shall not be used as a means of access.    (a) Building No. 3 - On or about March 30, 2016 employee used the crossbraces of a scaffold to climb down to the ground.       - East Side.  One bay scaffolding. 7 feet wide x 30 feet high (5 sections high)     - North side. Two bay scaffolding. 14 feet wide x 30 feet high (5 sections high)  - West Side. One bay scaffolding. 7 feet wide x 30 feet (5 sections high)
Recent events (3)
  • — A (S) $2800
  • — I (S) $1635
  • — Z (S) $2800

1926.451 G04 I

Serious Gravity 10 1 instance 1 exposed
Issued
Apr 28, 2016
Penalty
Initial $2,800 · Current $2,800
29 CFR 1926.451(g)(4)(i): Guardrail systems shall be installed along all open sides and ends of platforms. Guardrail systems shall be installed before the scaffold is released for use by employees other than erection/dismantling crews.    (a) Building No. 3 - On or about March 30, 2016 employee was cleaning an exterior brick wall while working from scaffolding that did not have guardrails.    - East Side.  One bay scaffolding. 7 feet wide x 30 feet high (5 sections high)     - North side. Two bay scaffolding. 14 feet wide x 30 feet high (5 sections high)  - West Side. One bay scaffolding. 7 feet wide x 30 feet (5 sections high)
Recent events (3)
  • — A (S) $2800
  • — I (S) $1635
  • — Z (S) $2800

1910.1200 E01

Other-than-serious 1 instance 1 exposed
Issued
Apr 28, 2016
Abate by
Jun 13, 2016
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(e)(1): Employers shall develop, implement, and maintain at each workplace, a written hazard communication program which at least describes how the criteria specified in paragraphs (f), (g), and (h) of this section for labels and other forms of warning, safety data sheets, and employee information and training will be met, and which also includes the following:  (a)  Building No. 3 - On or about March 30, 2016 employee was exposed to health hazards while mixing and applying Muriatic acid to be used in cleaning brick masonry. The employer had not developed a written hazard communication program.
Recent events (3)
  • — A (O) $0
  • — I (O) $0
  • — Z (O) $0

1910.1200 H01

Other-than-serious 1 instance 1 exposed
Issued
Apr 28, 2016
Abate by
Jun 13, 2016
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(h)(1): Employers shall provide employees with effective information and training on hazardous chemicals in their work area at the time of their initial assignment, and whenever a new physical or health hazard the employees have not previously been trained about is introduced into their work area. Information and training may be designed to cover categories of hazards (e.g., flammability, carcinogenicity) or specific chemicals. Chemical-specific information must always be available through labels and material safety data sheets.   (a)  Building No. 3 - On or about March 30, 2016 employee was exposed to health hazards while mixing and applying Muriatic acid to be used in cleaning brick masonry. The employer did not provide hazardous communication training to the exposed employee.
Recent events (3)
  • — A (O) $0
  • — I (O) $0
  • — Z (O) $0

1910.1200 G08

Other-than-serious 1 instance 1 exposed
Issued
Apr 28, 2016
Abate by
Jun 13, 2016
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(g)(8): The employer shall maintain in the workplace copies of the required safety data sheets for each hazardous chemical, and shall ensure that they are readily accessible during each work shift to employees when they are in their work area(s). (Electronic access and other alternatives to maintaining paper copies of the safety data sheets are permitted as long as no barriers to immediate employee access in each workplace are created by such options.)   (a)  Building No. 3 - On or about March 30, 2016 employee was exposed to health hazards while mixing and applying Muriatic acid to be used in cleaning brick masonry. Safety data sheets for muriatic acid was not accessible onsite.
Recent events (3)
  • — A (O) $0
  • — I (O) $0
  • — Z (O) $0

View J P Construction's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 341366938.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.