OSHA Inspection: WILLIAMS CONSTRUCTION

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of WILLIAMS CONSTRUCTION in 2748 LOVE ROAD, LEXINGTON, MS 39095 (NAICS 238140). OSHA activity number 344191010.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Williams Construction — free Get an email when a new federal OSHA severe-injury report for Williams Construction is published. One employer, no account, unsubscribe in one click.
Site address
2748 LOVE ROAD
City
LEXINGTON
State
MS
ZIP
39095
Mailing
2748 LOVE ROAD, LEXINGTON, MS 39095
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238140
Employees
8
Ownership type
A

10 citations on file for this inspection.

1910.1200 E01

Serious Gravity 1 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $1,705 · Current $1,705
29 CFR 1910.1200(e)(1): The employer did not develop, implement, and/or maintain at the workplace a written hazard communication program which describes how the criteria specified in 29 CFR 1910.1200(f), (g), and (h) will be met: (Construction Reference: 1926.59)  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 employees were working with masonry cement and the employer did not have a hazard communication program in place.
Recent events (1)
  • — Z (S) $1705

1910.1200 H01

Serious Gravity 1 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(h)(1): Employees were not provided effective information and training on hazardous chemicals in their work area at the time of their initial assignment and whenever a new hazard that the employees had not been previously trained about was introduced into their work area: (Construction Reference: 1926.59)  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 employees were working with masonry cement and the employer did not train employees as required on hazardous chemicals in the workplace.
Recent events (1)
  • — Z (S) $0

1910.1200 G08

Serious Gravity 1 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $0 · Current $0
29 CFR 1910.1200(g)(8): The employer did not maintain copies of the required safety data sheets for each hazardous chemical in the workplace: (Construction Reference: 1926.59)  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 employees were working with masonry cement and concrete blocks and the employer did not have safety data sheets for chemical products handled by employees.
Recent events (1)
  • — Z (S) $0

1926.451 A06

Serious Gravity 10 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $3,978 · Current $3,978
29 CFR 1926.451(a)(6): Scaffolds were not designed by a qualified person and were not constructed and loaded in accordance with that design:  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 employees were working on a fabricated frame scaffold which were missing mid-rail(s), was not fully planked and had missing guardrails exposing them to a fall hazard of approximately 12 feet to the ground.
Recent events (1)
  • — Z (S) $3978

1926.451 B01

Serious Gravity 5 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $2,273 · Current $2,273
29 CFR 1926.450(b)(1):  Each platform on all working levels of scaffolds was not fully planked or decked between the front uprights and the guardrail supports:  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 employees were observed working from a scaffold that was not fully planked exposing employees to a fall hazard.
Recent events (1)
  • — Z (S) $2273

1926.451 G01

Serious Gravity 10 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $3,978 · Current $3,978
29 CFR 1926.451(g)(1): 29 CFR 1926.451(g)(1): Each employee on a scaffold more than 10 feet (3.1m) above a lower level was not protected from falling to that lower level by fall protection established in accordance with paragraphs (g)(1)(i) through (vii) of this section:  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 employees were working from a fabricated frame scaffold without fall protection, exposing them to a fall hazard.
Recent events (1)
  • — Z (S) $3978

1926.451 H01

Serious Gravity 5 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $0 · Current $0
29 CFR 1926.451(h)(1): Each employee on a scaffold was not provided with additional protection from falling hand tools, debris, and other small objects through the installation of toeboards, screens, guardrail systems, or through the erection of debris nets, catch platforms, or canopy structures that contain or deflect the falling objects.  For falling objects too large, heavy or massive to be contained or deflected, the employer did not place and secure such potential falling objects away from the edge of the surface from which they could fall.  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 the employer did not ensure toe boards were in place on scaffolding, exposing employees working below scaffolds to over head hazards.
Recent events (1)
  • — Z (S) $0

1926.454 A

Serious Gravity 5 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $3,410 · Current $3,410
29 CFR 1926.454(a): The employer did not have each employee who performed work while on a scaffold trained by a person qualified in the subject matter to recognize the hazards associated with the type of scaffold being used and to understand the procedures to control or minimize those hazards.  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 the employer did not ensure employees were trained by a competent person to recognize hazards while working on scaffolds, exposing employees to a fall hazard of approximately 12 feet to the ground.
Recent events (1)
  • — Z (S) $3410

1926.501 B01

Serious Gravity 5 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $2,842 · Current $2,842
29 CFR 1926.501(b)(1): Each employee on a walking/working surface with an unprotected side or edge which was 6 feet (1.8 m) or more above a lower level was not protected from falling by the use of guardrail systems, safety net systems, or personal fall arrest systems.  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 employees working from the edge of a roof did not have any type of fall protection, exposing them to a fall hazard.
Recent events (1)
  • — Z (S) $2842

1926.50 D01

Other-than-serious 1 instance 8 exposed
Issued
Sep 20, 2019
Abate by
Oct 7, 2019
Penalty
Initial $0 · Current $0
29 CFR 1926.50(d)(1): First-aid supplies were not easily accessible when required:  (a) 213 Brooks St, Pelahatchie MS - On or about July 25, 2019 employees construction work activities and the employer did not have 1st aid supplies available at the worksite.
Recent events (1)
  • — Z (O) $0

View Williams Construction's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 344191010.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.