Safety Incidents OSHA Severe Injury Reports · 2015–2025
5,189,992Inspections Most recent open 2026-07-18 Last loaded 2026-07-22

OSHA Inspection: WSZ FRAMING INC

Planned inspection · Safety discipline

On , OSHA opened a planned safety inspection of WSZ FRAMING INC in 146 PARK AVE, ALLENDALE, NJ 07401 (NAICS 238130). OSHA activity number 345805345.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch WSZ Framing INC — free Get an email when a new federal OSHA severe-injury report for WSZ Framing INC is published. One employer, no account, unsubscribe in one click.
Establishment
WSZ FRAMING INC
Site address
146 PARK AVE
City
ALLENDALE
State
NJ
ZIP
07401
Mailing
147 BRICHWOOD DR, ELMWOOD PARK, NJ 07407
Inspection type
Planned (H)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
238130
Employees
7
Ownership type
A

4 citations on file for this inspection.

1926.1053 B01

Serious Gravity 10 1 instance 2 exposed
Issued
Mar 16, 2022
Penalty
Initial $4,786 · Current $2,393 Reduced
29 CFR  1926.1053(b)(1): Where portable ladders were used for access to an upper landing surface and the ladder's length allows, the ladder side rails did not extend at least 3 feet (.9 m) above the upper landing surface being accessed:  a) Exterior of Building, (Rear of Structure): Employees engaged in interior framing activities were exposed to fall hazards of approximately 15ft  while using a portable aluminum extension ladder for access whose ladder side rails were not raised 3ft above the upper landing surface.  Condition noted on or about 2/28/2022.
Recent events (3)
  • — F (S) $2393
  • — C (S) $4786
  • — Z (S) $4786

1926.602 D

Repeat Gravity 10 1 instance 1 exposed
Issued
Mar 16, 2022
Penalty
Initial $9,571 · Current $0 Reduced
29 CFR 1926.602(d): The employer did not certify that each operator had been trained and evaluated as required by paragraph 29 CFR 1910.178(l):Note: The requirements applicable to construction work under paragraph (d) of this section are identical to those set forth at paragraph (l) of 29 CFR 1910.178.     a) Exterior of Building - Back of House: The employer did not ensure that the operator of the all terrain forklift was certified, on or about 02/28/2022.  WSZ Framing, LLC was previously cited for serious violations of this Occupational Safety and Health standard or its equivalent standard, 29 CFR 1926.602(d): which was contained in OSHA Inspection Number 1272874, Citation # 1, Item # 4, issued on 04/17/2018 with respect to a workplace located at 111 Virginia Ave, Clifton NJ 07012. This citation became a final order on 5/07/2018.
Recent events (3)
  • — F (R) $0
  • — C (R) $9571
  • — Z (R) $9571

1926.501 B13

Willful Gravity 10 1 instance 1 exposed
Issued
Mar 16, 2022
Penalty
Initial $31,906 · Current $15,953 Reduced
29 CFR  1926.501(b)(13): Employees engaged in residential construction activities 6 feet (1.8m) or more above the lower levels were not protected by guardrail systems, safety net systems, or personal fall arrest systems:   a) Exterior of Building, (Rear of Structure): An employee engaged in roofing activities on a 6 on 12 pitched roof was exposed to fall hazards of approximately 18-20ft to the ground below as a means of fall protection was not utilized.  Condition noted on or about 2/28/2022.
Recent events (3)
  • — F (W) $15953
  • — C (W) $31906
  • — Z (W) $31906

1926.602 C01 VI

Willful Gravity 10 1 instance 1 exposed
Issued
Mar 16, 2022
Penalty
Initial $31,906 · Current $15,953 Reduced
29 CFR 1926.602(c)(1)(vi): Industrial truck(s) in use did not meet the applicable requirements of design, construction, stability, inspection, testing, maintenance, and operation, as defined in American National Standards Institute B56.1-1969, Safety Standards for Powered Industrial Trucks.  a- Building Exterior (Rear): A JLG- Lull Front end loader was used to raise an employee on a wooden pallet and left unattended with the hoisting boom fully raised as the outriggers remained unsecured above the second floor with a load of roofing materials. Condition observed on or about 02/28/2022.
Recent events (3)
  • — F (W) $15953
  • — C (W) $31906
  • — Z (W) $31906

View WSZ Framing INC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345805345.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.