BERNVILLE, PA —
OSHA Inspection: B & D MASONRY, INC.
Unprogrammed Other inspection · Safety discipline
At a glance
On , OSHA opened an unprogrammed Other safety inspection of B & D MASONRY, INC. in 430 NEW SCHEFFERSTOWN ROAD, BERNVILLE, PA 19506 (NAICS 238140). OSHA activity number 347457889.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- B & D MASONRY, INC.
- Site address
- 430 NEW SCHEFFERSTOWN ROAD
- City
- BERNVILLE
- State
- PA
- ZIP
- 19506
- Mailing
- 1201 MARSHALL AVENUE, LANCASTER, PA 17601
What kind of inspection was it?
- Inspection type
- Unprogrammed Other (I)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- B
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 238140
- Employees
- 8
- Ownership type
- A
Citations
4 citations on file for this inspection.
1926.50 G
- Issued
- Jul 24, 2024
- Abate by
- Aug 7, 2024
- Penalty
- Initial $4,610 · Current $4,000 Reduced
General-duty citation text
29 CFR 1926.50(g): Where employees were exposed to injurious corrosive materials, suitable facilities for quick drenching or flushing of the eyes and body were not provided within the work area for immediate emergency use: a. Tulpehocken Jr. & Sr. High School - On or about May 3, 2024, employees engaged in masonry work, mixing and applying mortar which included Portland Cement, employees were exposed to the corrosive nature of Portland Cement without quick drench and flushing equipment. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $4000
- — Z (S) $4610
1926.300 B04 II
- Issued
- Jul 24, 2024
- Abate by
- Aug 7, 2024
- Penalty
- Initial $4,610 · Current $4,000 Reduced
General-duty citation text
29 CFR 1926.300(b)(4)(ii): The point of operation of machine(s) whose operation exposed an employee to injury was not guarded: a. Mixing Area - On or about May 3, 2024, employees were mixing mortar using the Mud Hog MH20 mixer, the machine had an agitator in it where water and the mortar powder were combined to make the final product which was used for masonry work. The employees were exposed to a caught in hazard. b. Mixing Area - On or about May 3, 2024, employees were mixing mortar using the Essick Plaster mortar mixer serial #C1420104, the machine had an agitator in it where water and the mortar powder were combined to make the final product which was used for masonry work. The employees were exposed to a caught in hazard. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $4000
- — Z (S) $4610
1926.451 F07
- Issued
- Jul 24, 2024
- Abate by
- Aug 7, 2024
- Penalty
- Initial $5,531 · Current $4,000 Reduced
General-duty citation text
29 CFR 1926.451(f)(7): Scaffolds were not erected, moved, dismantled, or altered, by trained and experienced employees under the supervision and direction of a competent person qualified in scaffold erection, moving, dismantling or alteration: a. Tulpehocken Jr. & Sr. High School - On or about May 3, 2024, the employees were working on a Bil-Jax fabricated frame scaffold, the scaffold had a support tier, and two working tiers, with a side bracket. The side brackets and tiers were not joined with couplings or stacking pins or other equivalent means which a trained and competent person failed to identify and resolve prior to employees being exposed to a stuck-by and caught in hazard from structural collapse. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (O) $4000
- — Z (S) $5531
1926.452 C03
- Issued
- Jul 24, 2024
- Abate by
- Aug 7, 2024
- Penalty
- Initial $5,531 · Current $0 Reduced
General-duty citation text
29 CFR 1926.452(c)(3): Frames and panels were not joined together vertically by coupling or stacking pins or equivalent means: a. Tulpehocken Jr. & Sr. High School - On or about May 3, 2024, the employees were working on a Bil-Jax fabricated frame scaffold, the scaffold had a support tier, and two working tiers, with a side bracket. The side brackets and tiers were not joined with couplings or stacking pins or other equivalent means. Employees were exposed to a stuck-by and caught in hazard from structural collapse. Abatement certification required within 10 days after abatement date. The certification shall include a statement that abatement is complete, date and method of abatement, and states employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $5531
More inspections at B & D Masonry, INC.
View B & D Masonry, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 238140)
More inspections in PA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 347457889.