On , OSHA opened a planned safety inspection of MAURO SEWER CONSTRUCTION, INC. in 630 8TH STREET, WILMETTE, IL 60091 (NAICS 237110). OSHA activity number 347794885.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MAURO SEWER CONSTRUCTION, INC.
- Site address
- 630 8TH STREET
- City
- WILMETTE
- State
- IL
- ZIP
- 60091
- Mailing
- 1251 REDEKER RD., DES PLAINES, IL 60016
What kind of inspection was it?
- Inspection type
- Planned (H)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- A
When did the case open and close?
- Opened
- Closing conference
- Last modified
- Data loaded
Establishment context
- NAICS code
- 237110
- Employees
- 21
- Ownership type
- A
Citations
9 citations on file for this inspection.
1926.102 A01
- Issued
- Mar 13, 2025
- Penalty
- Initial $6,242 · Current $8,000
General-duty citation text
29 CFR 1926.102(a)(1): The employer did not ensure employees used eye and face protection equipment when machines or operations presented potential eye or face injury from physical, chemical, or radiation agents: a) On October 3, 2024, at the above addressed jobsite, employees were exposed to eye injury while using a saw to cut ductile iron pipe without eye protection. No abatement certification or documentation is required for this item.
Recent events (3)
- — F (O) $8000
- — C (S) $6242
- — Z (S) $6242
1926.651 C02
- Issued
- Mar 13, 2025
- Penalty
- Initial $7,282 · Current $8,000
General-duty citation text
1926.21(b)(2): The employer did not instruct each employee in the recognition and avoidance of unsafe conditions and the regulations applicable to his work environment to control or eliminate any hazards or other exposure to illness or injury. a) On October 3, 2024, at the above addressed jobsite, while a ladder was being repositioned within an excavation of approximately eight feet, the employer?s instruction to affected employees on safe practices was not effective. No abatement certification or documentation is required for this item.
Recent events (3)
- — F (S) $8000
- — C (S) $7282
- — Z (S) $7282
1926.651 E
- Issued
- Mar 13, 2025
- Abate by
- Apr 8, 2025
- Penalty
- Initial $7,282 · Current $7,282
General-duty citation text
29 CFR 1926.651(e): Employee was not prohibited to be underneath loads handled by lifting or digging equipment: a) On October 3, 2024, employees were exposed to struck-by and crushing hazards while performing work underneath loads being lowered into excavation by the excavating equipment. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
- — F (O) $7282
- — C (S) $7282
- — Z (S) $7282
1926.651 L
- Issued
- Mar 13, 2025
- Abate by
- Apr 8, 2025
- Penalty
- Initial $5,202 · Current $8,000
General-duty citation text
29 CFR 1926.651(l): Walkways were not provided where employees or equipment were required or permitted to cross over excavations: a) On October 3, 2024, at the above addressed jobsite, employees were exposed to hazards of falling into open excavation when crossing over the excavation. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
- — F (S) $8000
- — C (S) $5202
- — Z (S) $5202
1926.652 G01 II
- Issued
- Mar 13, 2025
- Abate by
- Apr 8, 2025
- Penalty
- Initial $7,282 · Current $0 Reduced
General-duty citation text
29 CFR 1926.652(g)(1)(ii): Shields were not installed in a manner to restrict lateral or other hazardous movement of the shield in the event of the application of sudden lateral loads: a) On October 3, 2024, at the above addressed jobsite, the employer did not ensure that shields, such as the Manhole Box #12126, were installed to restrict movement in the event of trench wall collapse which would put sudden lateral loads on the side shields. The Manhole Box #12126 was occupied by employees while being suspended from an excavator and was not secured to prevent movement during an unexpected event of lateral loads. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
- — F (S) $0
- — C (S) $7282
- — Z (S) $7282
1926.1053 B06
- Issued
- Mar 13, 2025
- Abate by
- Apr 8, 2025
- Penalty
- Initial $4,161 · Current $0 Reduced
General-duty citation text
29 CFR 1926.1053(b)(6): Ladders were used on surfaces which were not stable and level: a) On October 3, 2024, at the above addressed jobsite, the employer did not ensure that all ladders, including the Werner Fiberglass Extension Ladder, were positioned with even and level footing when provided for use by employees. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
- — F (S) $0
- — C (S) $4161
- — Z (S) $4161
1926.652 A01
- Issued
- Mar 13, 2025
- Abate by
- Apr 8, 2025
- Penalty
- Initial $109,239 · Current $75,268 Reduced
General-duty citation text
29 CFR 1926.652(a)(1): Each employee in an excavation was not protected from cave-ins by an adequate protective system designed in accordance with 29 CFR 1926.652 (b) or (c). a) On October 3, 2024, at the above address, an employee was exposed to cave-in hazards while performing work in an unprotected trench/excavation of approximately seven feet eight inches in depth. The employer did not ensure that employees were protected from cave-in hazards. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
- — F (W) $75268
- — C (W) $109239
- — Z (W) $109239
1926.652 G02
- Issued
- Mar 13, 2025
- Abate by
- Apr 8, 2025
- Penalty
- Initial $12,485 · Current $8,000 Reduced
General-duty citation text
29 CFR 1926.652(g)(2): Excavations of earth material to a level no greater than 2 feet (.61m) below the bottom of a shield was permitted: a) On October 3, 2024, at the above addressed jobsite, the employer permitted its employees to enter the trench and perform work when the earth material was excavated approximately three feet six inches below the bottom of the support system. Mauro Sewer Construction, Inc. was previously cited for a violation of the equivalent occupational safety and health standard 1926.652(e)(2)(i), which was contained in OSHA inspection number 1646871, citation number 1, item number 2 and was affirmed as a final order on March 9, 2023, with respect to a workplace located at 236 S Richmond Avenue in Westmont, Illinois. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
- — F (S) $8000
- — C (R) $12485
- — Z (R) $12485
1926.652 C03 III
- Issued
- Mar 13, 2025
- Abate by
- Apr 8, 2025
- Penalty
- Initial $2,080 · Current $2,000 Reduced
General-duty citation text
29 CFR 1926.652(c)(3)(iii): At least one copy of the tabulated data, which identifies the registered professional engineer who approved the data, was not maintained at the jobsite during construction of the protective system: a) On October 3, 2024, at the above addressed jobsite, the employer did not maintain a copy of the tabulated data for the trench shields used at the site including Trench Box #13630 and Manhole Box #12126. Mauro Sewer Construction, Inc. was previously cited for a violation of the equivalent occupational safety and health standard 1926.652(c)(3)(iii), which was contained in OSHA inspection number 1704315, citation number 2, item number 1c and was affirmed as a final order on October 25, 2023, with respect to a workplace located at 310 Arlington Heights Road in Avenue in Arlington Heights, Illinois. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the CERTIFICATION OF CORRECTIVE ACTION WORKSHEET), and in addition, documentation demonstrating that abatement is complete must be included with your certification. This documentation may include, but is not limited to, evidence of the purchase or repair of the equipment, photographic or video evidence of abatement, or other written records.
Recent events (3)
- — F (O) $2000
- — C (R) $2080
- — Z (R) $2080
More inspections at Mauro Sewer Construction, INC.
View Mauro Sewer Construction, INC.'s full OSHA safety record →
More inspections in this industry (NAICS 237110)
More inspections in IL
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 347794885.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.