WATERFORD, NY —
OSHA Inspection: MOMENTIVE PERFORMANCE MATERIALS
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of MOMENTIVE PERFORMANCE MATERIALS in 260 HUDSON RIVER ROAD, WATERFORD, NY 12188 (NAICS 325211). OSHA activity number 313758542.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- MOMENTIVE PERFORMANCE MATERIALS
- Site address
- 260 HUDSON RIVER ROAD
- City
- WATERFORD
- State
- NY
- ZIP
- 12188
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- Y
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 325211
- SIC code (legacy)
- 2821
- Employees
- 1000
- Ownership type
- A
Citations
8 citations on file for this inspection.
1910.119 D03 II
- Issued
- Oct 18, 2010
- Abate by
- May 15, 2011
- Penalty
- Initial $4,500 · Current $7,000
General-duty citation text
Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to inhalation and burn hazards resulting from an uncontrolled release of sulfuric acid: (a)MeCl Process, Railcar Station no. 1, on or about 4/25/10: Sulfuric acid transfer hose assembly was not adequately designed, installed, and maintained to protect employees from an uncontrolled release of sulfuric acid. Abatement note: Among other methods, one feasible means of abatement for this hazard would be the installation of a remote-operated valve (ROV) or similar device, located at the transfer hose connection to the railcar. Pursuant to 29 CFR 1903.19(d), the employer must provide documentation and certification to OSHA that this violation has been abated within 10 calendar days of the "Date by which Violation Must be Abated".
Recent events (2)
- — F (O) $7000.00
- — Z (S) $4500.00
1910.119 D03 II
- Issued
- Oct 18, 2010
- Abate by
- Nov 22, 2010
- Penalty
- Initial $4,500 · Current $4,500
General-duty citation text
29 CFR 1910.119(d)(3)(ii): The employer did not document that the equipment in the process complied with recognized and generally accepted good engineering practices: (a)MeCl Process, Train A, Building 34A: Employer failed to document that relief systems complied with recommended and generally accepted good engineering practice(s), such as API 520 Part II, including, but not limited to: PSV-5205, PSV-5241, PSV-5245, and PSV-5253, when the inlet pressure drop exceeded 3% of the set point, on or about 5/25/10. (a)MeCl Process, Train A, Building 34A: Employer failed to document that relief systems complied with recommended and generally accepted good engineering practice(s), such as API 520 Part I, including, but not limited to: PSV-5205, when the outlet pressure drop exceeded 10% of the set point, on or about 5/25/10. Abatement note: The employer should document that all relief systems in the MeCl unit are properly verifed for compliance with API 520 part I and II. Pursuant to 29 CFR 1903.19(d), the employer must provide documentation and certification to OSHA that this violation has been abated within 10 calendar days of the "Date by which Violation Must be Abated".
Recent events (2)
- — F (S) $4500.00
- — Z (S) $4500.00
1910.119 E03 V
- Issued
- Oct 18, 2010
- Abate by
- Nov 22, 2010
- Penalty
- Initial $4,500 · Current $4,500
General-duty citation text
29 CFR 1910.119(e)(3)(v): The process hazard analysis did not address facility siting: (a)MeCl process, Trains A & B, on or prior to 6/10/10: The PHA did not address facility siting hazards which could result in personnel exposure to MeCl vapor in the process area, including, but not limited to: -Hazards associated with location of safety relief valve atmospheric vents immediately adjacent to personnel work platforms on 7th deck; -Hazards associated with installation of a wind protection barrier which partially enclosed the structure on the A train side; -Hazards associated with lack or limitations of vapor detectors/alarms or other suitable means of warning employees of a vapor leak or release; -Hazards associated with location of emergency escape respirators. Pursuant to 29 CFR 1903.19(d), the employer must provide documentation and certification to OSHA that this violation has been abated within 10 calendar days of the "Date by which Violation Must be Abated".
Recent events (2)
- — F (S) $4500.00
- — Z (S) $4500.00
1910.119 E03 VI
- Issued
- Oct 18, 2010
- Abate by
- Nov 22, 2010
- Penalty
- Initial $4,500 · Current $4,500
General-duty citation text
29 CFR 1910.119(e)(3)(vi): The process hazard analysis did not address human factors: (a)MeCl process, Trains A & B: The Process Hazard Analysis did not address hazard(s) associated with limited staffing in the control room while operators are performing a rail car switch, on or about 5/7/10. (b)MeCl process, Trains A & B: The Process Hazard Analysis did not address hazard(s) associated with operator fatigue and shift length, on or about 5/7/10. (c)MeCl process, Trains A & B: The Process Hazard Analysis did not address shift staffing and operator failure to follow the established shift change procedure for the MeCl/Siloxanes unit, on or about 5/7/10. Pursuant to 29 CFR 1903.19(d), the employer must provide documentation and certification to OSHA that this violation has been abated within 10 calendar days of the "Date by which Violation Must be Abated".
Recent events (2)
- — F (S) $4500.00
- — Z (S) $4500.00
1910.119 E05
- Issued
- Oct 18, 2010
- Abate by
- Nov 22, 2010
- Penalty
- Initial $4,500 · Current $4,500
General-duty citation text
29 CFR 1910.119(e)(5): Them employer did not assure that actions recommended by the process hazard analysis team are resolved in a timely manner and that the resolution is documented: (a)MeCl Process, Trains A & B: Employer failed to ensure that all recommendations from the previous process hazard analysis were completed as soon as possible, in that PHA recommendations from 2004 study were still open, on or prior to 5/7/10. (b)MeCl Process, Trains A & B: Employer failed to document the resolution of all PHA recommendations from 2004 PHA study, in that the resolution of recommendation no. 8 "consider installation of a flame arrestor at MeOH high point vent" was not documented, on or prior to 6/5/10. Pursuant to 29 CFR 1903.19(d), the employer must provide documentation and certification to OSHA that this violation has been abated within 10 calendar days of the "Date by which Violation Must be Abated".
Recent events (2)
- — F (S) $4500.00
- — Z (S) $4500.00
1910.119 F03
- Issued
- Oct 18, 2010
- Abate by
- Nov 22, 2010
- Penalty
- Initial $4,500 · Current $7,000
General-duty citation text
29 CFR 1910.119(f)(3): The operating procedures were not reviewed as often as necessary to assure that they reflect current operating practice, including changes that result from changes in process chemicals, technology, and equipment, or changes to facilities: (a)MeCl Process, A train: Employer failed to ensure that operating procedures were reviewed as often as necessary to ensure that they reflect current operating practice, including but not limited to: Chem-Ops East Plant Operating Manual, section 4.3.3.2, Critical Alarms, where documentation of high and low alarms did not reflect current alarm high and low set points for the following selected instruments: PIC-5149, LIC-5064, PT-5142, PT-5112, PT-5107, FFC-5010, and FIC-5013, on or about 6/10/10. Pursuant to 29 CFR 1903.19(d), the employer must provide documentation and certification to OSHA that this violation has been abated within 10 calendar days of the "Date by which Violation Must be Abated".
Recent events (2)
- — F (S) $7000.00
- — Z (S) $4500.00
1910.119 J06 II
- Issued
- Oct 18, 2010
- Abate by
- Nov 22, 2010
- Penalty
- Initial $4,500 · Current $7,000
General-duty citation text
29 CFR 1910.119(j)(6)(ii): Appropriate checks and inspections were not performed to assure that equipment was installed properly and consistent with design specifications and the manufacturer's instructions: (a)MeCl Process, Train B: Employer failed to ensure that appropriate checks and inspections were performed, in that: short bolts were found on three manway covers on vessel 340042 (methanol recovery column B2), on or about 6/9/10. (b)MeCl Process, Train A: Employer failed to ensure that appropriate checks and inspections were performed in that Pump inspection work orders were not reviewed/completed by supervisor, in some cases months after the work order was completed, for process pumps including, but not limited to: TSW-340438, TSW-341030, TSW-341021, and TSW-341025, on or prior to 5/18/10. Pursuant to 29 CFR 1903.19(d), the employer must provide documentation and certification to OSHA that this violation has been abated within 10 calendar days of the "Date by which Violation Must be Abated".
Recent events (2)
- — F (O) $7000.00
- — Z (S) $4500.00
1910.119 J06 III
- Issued
- Oct 18, 2010
- Abate by
- Oct 21, 2010
- Penalty
- Initial $4,500
General-duty citation text
29 CFR 1910.119(j)(6)(iii): The employer did not assure that maintenance materials, spare parts and equipment were suitable for the process application for which they were used: (a)MeCl Process: Employer did not ensure that maintenance materials, spare parts, and equipment were suitable for the process application for which they were used, including, but not limited to: Teflon manway cover gasket(s) and bolts on vessel 340042 (methanol recovery column B2), on or about 6/09/10.
Recent events (2)
- — F (O)
- — Z (S) $4500.00
More inspections at Momentive Performance Materials
View Momentive Performance Materials's full OSHA safety record →
More inspections in this industry (NAICS 325211)
More inspections in NY
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 313758542.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.