OSHA Inspection: WAUKESHA FOUNDRY, INC.

Monitoring inspection · Health discipline

On , OSHA opened a monitoring health inspection of WAUKESHA FOUNDRY, INC. in 1300 LINCOLN AVENUE, WAUKESHA, WI 53186 (NAICS 331513). OSHA activity number 341237378.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Waukesha Foundry, INC. — free Get an email when a new federal OSHA severe-injury report for Waukesha Foundry, INC. is published. One employer, no account, unsubscribe in one click.
Site address
1300 LINCOLN AVENUE
City
WAUKESHA
State
WI
ZIP
53186
Mailing
1300 LINCOLN AVENUE, WAUKESHA, WI 53186
Inspection type
Monitoring (D)
Scope
Partial (B)
Discipline
Health
Advance notice
No
Union status
A
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
331513
Employees
130
Ownership type
A

4 citations on file for this inspection.

1910.1000 A02

Serious Gravity 1 1 instance 1 exposed
Issued
Apr 6, 2016
Abate by
Jun 13, 2018
Penalty
Initial $2,295 · Current $2,295

Hazardous substances G301

29 CFR 1910.1000(a)(2): Employee(s) were exposed to an airborne concentration of particulates not otherwise regulated - total dust listed in Table Z-1 in excess of the 8-hour Time Weighted Average concentration of 15 milligrams per cubic meter (mg/m3):      (a)     The arc air and plasma cutting operator was exposed to Particulates Not Otherwise Regulated - Total Dust at an 8-hour time weighted average of 20.0 mg/m3, approximately 1.4 times the limit of 15 mg/m3; this limit is established to prevent respiratory irritation.  The samples were collected on February 23, 2016 during a 456 minute sampling period.  Exposure calculations include a zero increment for the 24 minutes not sampled.
Recent events (4)
  • — P (S) $2295
  • — P (S) $2295
  • — I (S) $2295

1910.1000 E

Serious Gravity 1 1 instance 1 exposed
Issued
Apr 6, 2016
Abate by
Jun 13, 2019
Penalty
Initial $0 · Current $0

Hazardous substances G301

29 CFR 1910.1000(e): Feasible administrative or engineering controls were not determined and implemented to achieve compliance with the limits prescribed in 29 CFR 1910.1000(a) through (d):    (a)     The arc air and plasma cutting operator was exposed to Particulates Not Otherwise Regulated - Total Dust at an 8-hour time weighted average of 20.0 mg/m3, approximately 1.4 times the limit of 15 mg/m3; this limit is established to prevent respiratory irritation.  The samples were collected on February 23, 2016 during a 456 minute sampling period.  Exposure calculations include a zero increment for the 24 minutes not sampled.
Recent events (5)
  • — P (S) $0
  • — P (S) $0
  • — P (S) $0

1910.1000 A02

Serious Gravity 5 1 instance 1 exposed
Issued
Apr 6, 2016
Abate by
Jun 13, 2018
Penalty
Initial $3,825 · Current $0 Reduced

Hazardous substances 1840

29 CFR 1910.1000(a)(2): Employee(s) were exposed to an airborne concentration of Nickel, Metal and Insoluble Compounds (as Ni) listed in Table Z-1 in excess of the 8-hour Time Weighted Average concentration of 1.0 milligrams per cubic meter (mg/m3):      (a)     The arc air and plasma cutting operator was exposed to Nickel, Metal and Insoluble Compounds (as Ni) at an 8-hour time weighted average of 4.3 mg/m3, approximately 4.3 times the limit of 1.0 mg/m3; this limit is established to prevent nasal, sinus and lung cancer.  The samples were collected on February 23, 2016 during a 456 minute sampling period.  Exposure calculations include a zero increment for the 24 minutes not sampled.
Recent events (4)
  • — P (S) $0
  • — P (S) $0
  • — I (S) $0

1910.1000 E

Serious Gravity 5 1 instance 1 exposed
Issued
Apr 6, 2016
Abate by
Jun 13, 2019
Penalty
Initial $0 · Current $0

Hazardous substances 1840

29 CFR 1910.1000(e): Feasible administrative or engineering controls were not determined and implemented to achieve compliance with the limits prescribed in 29 CFR 1910.1000(a) through (d):    (a)     The arc air and plasma cutting operator was exposed to Nickel, Metal and Insoluble Compounds (as Ni) at an 8-hour time weighted average of 4.3 mg/m3, approximately 4.3 times the limit of 1.0 mg/m3; this limit is established to prevent nasal, sinus and lung cancer.  The samples were collected on February 23, 2016 during a 456 minute sampling period.  Exposure calculations include a zero increment for the 24 minutes not sampled.
Recent events (5)
  • — P (S) $0
  • — P (S) $0
  • — P (S) $0

View Waukesha Foundry, INC.'s full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 341237378.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.