CORRY, PA —
OSHA Inspection: CORRY RUBBER CORPORATION
Complaint inspection · Safety discipline
At a glance
On , OSHA opened a complaint safety inspection of CORRY RUBBER CORPORATION in 601 W. MAIN STREET, CORRY, PA 16407 (NAICS 325212). OSHA activity number 348333360.
OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.
Where did this inspection happen?
- Establishment
- CORRY RUBBER CORPORATION
- Site address
- 601 W. MAIN STREET
- City
- CORRY
- State
- PA
- ZIP
- 16407
- Mailing
- 601 W. MAIN STREET, CORRY, PA 16407
What kind of inspection was it?
- Inspection type
- Complaint (B)
- Scope
- Partial (B)
- Discipline
- Safety
- Advance notice
- No
- Union status
- A
When did the case open and close?
- Opened
- Closing conference
- Case closed
- Last modified
- Data loaded
Establishment context
- NAICS code
- 325212
- Employees
- 53
- Ownership type
- A
Citations
12 citations on file for this inspection.
1910.28 B01 I
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $11,585 · Current $4,000 Reduced
General-duty citation text
29 CFR 1910.28(b)(1)(i):Except as provided elsewhere in this section 29 CFR 1910.28, the employer did not ensure that each employee on a walking-working surface with an unprotected side or edge that is 4 feet (1.2 m) or more above a lower level is protected from falling by one or more of the systems described in 29 CFR 1910.28(b)(1)(i): a.) Corry Rubber Corporation, roof outside of paint shop access platform - On or about 6/25/25, and at times prior thereto, the guardrail on the roof had an opening of approximately 1 foot between the unsecured guardrail and the secured guardrail as it approached the landing platform where employees access the roof. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $4000
- — Z (S) $11585
1910.28 B13 III A
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.28(b)(13)(iii)(A): When work is performed 15 feet (4.6 m) or more from the roof edge, the employer did not protect each employee from falling by a guardrail system, safety net system, travel restraint system, or personal fall arrest system or a designated area. The employer is not required to provide any fall protection, provided the work is both infrequent and temporary. a.) Corry Rubber Corporation, roof outside of paint shop - On or about 6/25/25, and at times prior thereto, employees were required to walk outside of the guardrail system to grease the cooling tower fan. Employees do not have any type of fall protection when outside of the guardrail system. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.29 B03
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.29(b)(3): The employer did not ensure that guardrail systems are capable of withstanding, without failure, a force of at least 200 pounds (890 N) applied in a downward or outward direction within 2 inches (5 cm) of the top edge, at any point along the top rail. a.) Corry Rubber Corporation, roof outside of paint shop - On or about 6/25/25, and at times prior thereto, a guardrail on the roof was not secured to the roof. The railing was free standing and moved easily with any pressure applied to it. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.147 C04 II
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $5,627 · Current $3,000 Reduced
General-duty citation text
29 CFR 1910.147(c)(4)(ii):Procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, and the means to enforce compliance including, but not limited to, 29 CFR 1910.147(c)(4)(ii)(A), (c)(4)(ii)(B), (c)(4)(ii)(C) and (c)(4)(ii)(D): a.) Corry Rubber Corporation - On or about 6/25/25, and at times prior thereto, the lockout/tagout procedures did not list the magnitudes of energy. Energy sources, included, but were not limited to, mechanical, hydraulic and pneumatic. Employees perform servicing and maintenance on equipment including but not limited to cooling tower fan and presses. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $3000
- — Z (S) $5627
1910.147 C06 I
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.147(c)(6)(i):The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a.) Corry Rubber Corporation - On or about 6/25/25, and at times prior thereto, an periodic inspection of the lockout/tagout procedures had not been conducted. Employees perform servicing and maintenance on equipment including but not limited to cooling tower fan and presses. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.147 D
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.147(d):The established procedure for the application of energy control (the lockout or tagout procedures) did not cover the actions listed in and was not done in sequence as required by 29 CFR 1910.147(d)(1)-(6): b.) Corry Rubber Corporation - On or about 6/25/25, and at times prior thereto, employees did not lockout prior to servicing operations on equipment including, but not limited to, injection presses and manual presses. Employees are periodically required to perform set up and maintenance on the presses. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.147 C07 I
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.147(c)(7)(i): The employer did not provide adequate training to ensure that the purpose and function of the energy control program was understood by employees: a.) Corry Rubber Corporation - On or about 6/25/25, and at times prior thereto, the company did not provide lockout/tagout training to authorized employees who performed lockout/tagout on equipment including, but not limited to, presses. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.215 A04
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $5,627 · Current $3,000 Reduced
General-duty citation text
29 CFR 1910.215(a)(4): Work rest(s) on grinding machinery were not adjusted closely to the wheel with a maximum opening of one eighth inch: a.) Corry Rubber Corporation, maintenance department - On or about 6/25/25, and at times prior thereto, the Eagle bench grinder work rest was 1/2 inch away from the grinding wheel. Employees use the grinder weekly to sharpen lathe tooling. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $3000
- — Z (S) $5627
1910.215 B09
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.215(b)(9): The distance between the abrasive wheel periphery(s) and the adjustable tongue or the end of the safety guard peripheral member at the top exceeded one fourth inch: a.) Corry Rubber Corporation, maintenance department- on or about 6/25/25 and times prior thereto: The tongue guard for the grinding wheel on the Eagle bench grinder was positioned 3/4 inch away from the grinding wheel. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.303 B02
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $5,627 · Current $3,000 Reduced
General-duty citation text
29 CFR 1910.303(b)(2):Listed or labeled electrical equipment was not used or installed in accordance with instructions included in the listing or labeling: a.) Corry Rubber Corporation, upstairs paint room - On or about 6/25/25, and at times prior thereto, a surge protector was being used that was listed and labeled for household use only. The surge protector was powering fans in the adjacent room ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $3000
- — Z (S) $5627
1910.303 G01 II
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.303(g)(1)(ii):The required working space about electric equipment rated 600 volts, nominal, or less to ground, was used for storage: a.) Corry Rubber Corporation, 2nd floor sandblasting area - On or about 6/25/25, and at times prior thereto, the area in front of electrical panel boxes and electrical disconnects were used for storage. Items stored in front of the electrical equipment, included, but was not limited to, cardboard boxes of parts. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
1910.305 G01 IV A
- Issued
- Sep 30, 2025
- Abate by
- Dec 17, 2025
- Penalty
- Initial $0 · Current $0
General-duty citation text
29 CFR 1910.305(g)(1)(iv)(A): Flexible cords and/or cables were used as a substitute for the fixed wiring of a structure: a.) Corry Rubber Corporation, 2nd floor, sand blasting/paint room - On or about 6/25/25, and at times prior thereto, fans were being powered by extension cords that were run to a power tap and an electrical outlet. ABATEMENT CERTIFICATION REQUIRED: Abatement certification is required within 10 days after the abatement date noted on the citation (see below). This certification shall include a statement that abatement is complete, the date abatement was completed, method of abatement, and state that employees and their representatives were informed of this abatement.
Recent events (2)
- — I (S) $0
- — Z (S) $0
More inspections at Corry Rubber Corporation
View Corry Rubber Corporation's full OSHA safety record →
More inspections in this industry (NAICS 325212)
More inspections in PA
Source
This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 348333360.
Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.