OSHA Inspection: PENNEX ALUMINUM COMPANY LLC

Federal Agency inspection · Safety discipline

On , OSHA opened a federal Agency safety inspection of PENNEX ALUMINUM COMPANY LLC in 2205 PENNSYLVANIA AVENUE, YORK, PA 17404 (NAICS 331318). OSHA activity number 345681019.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Pennex Aluminum Company LLC — free Get an email when a new federal OSHA severe-injury report for Pennex Aluminum Company LLC is published. One employer, no account, unsubscribe in one click.
Site address
2205 PENNSYLVANIA AVENUE
City
YORK
State
PA
ZIP
17404
Mailing
2205 PENNSYLVANIA AVENUE ATTN: JEREMY MOLISON, YORK, PA 17404
Inspection type
Federal Agency (M)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
331318
Employees
80
Ownership type
A

5 citations on file for this inspection.

1910.303 B01 II

Other-than-serious Gravity 10 2 instances 80 exposed
Issued
May 4, 2022
Abate by
May 31, 2022
Penalty
Initial $13,052 · Current $13,052
29 CFR  1910.303(b)(1)(ii): Electrical equipment was not free from recognized hazards, based on the mechanical strength and durability, including, for parts designed to enclose and protect other equipment, the adequacy of the protection thus provided:   a) Warehouse Column 1, Mounted Outlet (20A/120V) - The metal conduit, faceplate (cover), and outlet box were not sufficiently durable for their location, or about December 2, 2021 and times prior thereto.  b) Warehouse Column 2, Mounted Outlet (20A/120V) - The metal conduit, faceplate (cover), and outlet box were not sufficiently durable for their location, on or about December 2, 2021 and times prior thereto.  Abatement certification and documentation required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.  Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (O) $13052
  • — Z (S) $13052

1910.303 B08 I

Other-than-serious Gravity 5 2 instances 80 exposed
Issued
May 4, 2022
Abate by
May 31, 2022
Penalty
Initial $0 · Current $0
29 CFR  1910.303(b)(8)(i): Electrical equipment was not firmly secured to the surface on which it was mounted:   a) Warehouse Column 1, Mounted Outlet (20A/120V) - The metal conduit was not secured to the column in at least two (2) locations, on or about December 2, 2021 and times prior thereto.  b) Warehouse Column 2, Mounted Outlet (20A/120V) - The metal conduit was not secured to the column in at least one (1) location, on or about December 2, 2021 and times prior thereto.  Abatement certification and documentation required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.  Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

1910.305 B01 II

Other-than-serious Gravity 5 2 instances 80 exposed
Issued
May 4, 2022
Abate by
May 31, 2022
Penalty
Initial $0 · Current $0
29 CFR  1910.305(b)(1)(ii): Unused openings in boxes, cabinets, or fittings were not effectively closed:   a) Warehouse Column 1, Mounted Outlet (20A/120V) - Each of the six (6) knockouts were not sealed tight against the metal box, on or about December 2, 2021 and times prior thereto.  b) Warehouse Column 2, Mounted Outlet (20A/120V) - Each of the six (6) knockouts were not sealed tight against the metal box, on or about December 2, 2021 and times prior thereto.   Abatement certification and documentation required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.  Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (O) $0
  • — Z (S) $0

1910.303 G02 II

Serious Gravity 5 2 instances 80 exposed
Issued
May 4, 2022
Abate by
May 31, 2022
Penalty
Initial $9,324 · Current $9,976
29 CFR  1910.303(g)(2)(ii): In locations where electric equipment was likely to be exposed to physical damage, enclosures or guards were not so arranged and of such strength as to prevent such damage:  a) Warehouse Column 1, Mounted Outlet (20A/120V) - A 20 amp/120-volt surface mounted outlet located 4 feet high above the floor was not protected from accidental contact or damage, on or about December 2, 2021 and times prior thereto.  b) Warehouse Column 2, Mounted Outlet (20A/120V) - A 20 amp/120-volt surface mounted outlet located 3 feet - 9 inches high above the floor was not protected from accidental contact or damage, on or about December 2, 2021 and times prior thereto.  Abatement certification and documentation required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.  Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (S) $9976.2
  • — Z (S) $9324

1910.333 A01

Deleted Serious Gravity 10 1 instance 1 exposed
Issued
May 4, 2022
Abate by
May 31, 2022
Penalty
Initial $13,052 · Current $0 Reduced
29 CFR  1910.333(a)(1): Live parts to which an employee may be exposed were not deenergized before the employee worked on or was near to them:   a) Warehouse Column 1, Mounted Outlet (20A/120V) - A damaged 20 amp/120-volt mounted outlet was not de-energized prior to inspection exposing the employee to electrical shock hazards, on or about December 2, 2021.  Abatement certification and documentation required within 10 days after abatement date.  The certification shall include a statement that abatement is complete, the date and method of abatement, and state that employees and their representatives were informed of this abatement.  Abatement documentation shall include documents demonstrating that abatement is complete, such as evidence of the purchase or repair of equipment, photographic or video evidence of abatement or other written records.
Recent events (2)
  • — I (S) $0
  • — Z (S) $13052

View Pennex Aluminum Company LLC's full OSHA safety record →

This record is reproduced from the U.S. Department of Labor Open Data API (OSHA inspection dataset). The original IMIS detail view is available at OSHA's Establishment Search for activity number 345681019.

Look up any company's OSHA accident reports by company, or browse severe injury reports by year, state, and company.