OSHA Inspection: PERRY FIBERGLASS PRODUCTS, INC.

Complaint inspection · Safety discipline

On , OSHA opened a complaint safety inspection of PERRY FIBERGLASS PRODUCTS, INC. in 33660 PIN OAK PARKWAY, AVON LAKE, OH 44012 (NAICS 326199). OSHA activity number 339585051.

What this inspection record means

OSHA opens inspections for many reasons — routine scheduling under a national or local emphasis program, an employee complaint or referral, or a follow-up after a reported injury. Opening or conducting an inspection is not itself an allegation or a finding that this employer broke any rule; any findings appear as the citations listed below, and citations can be contested, reduced, or withdrawn.

Watch Perry Fiberglass Products, INC. — free Get an email when a new federal OSHA severe-injury report for Perry Fiberglass Products, INC. is published. One employer, no account, unsubscribe in one click.
Site address
33660 PIN OAK PARKWAY
City
AVON LAKE
State
OH
ZIP
44012
Mailing
33660 PIN OAK PKWY., AVON LAKE, OH 44012
Inspection type
Complaint (B)
Scope
Partial (B)
Discipline
Safety
Advance notice
No
Union status
B
Opened
Closing conference
Case closed
Last modified
Data loaded
NAICS code
326199
Employees
68
Ownership type
A

7 citations on file for this inspection.

1910.106 E02 IV A

Serious Gravity 5 1 instance 6 exposed
Issued
Jul 23, 2014
Penalty
Initial $3,850 · Current $1,925 Reduced
29 CFR 1910.106(e)(2)(iv)(a): 29 CFR 1910.106(e)(2)(iv)(a): Category 1 or 2 flammable liquids, or Category 3 flammable liquids with a flashpoint below 100 °F (37.8 °C), were not kept in covered containers when not actually in use:    a)  Perry Fiberglass Products, Inc., Avon Lake, Ohio:  On or about February 13, 2014, the employer did not ensure that a Category 3 flammable resin was stored in a closed drum, exposing employee to fire and explosion hazards.  The open drum was located near Winder #2 in building #1.
Recent events (2)
  • — I (S) $1925
  • — Z (S) $3850

1910.133 A01

Serious Gravity 5 1 instance 6 exposed
Issued
Jul 23, 2014
Abate by
Aug 22, 2014
Penalty
Initial $4,620 · Current $2,310 Reduced
29 CFR 1910.133(a)(1): Protective eye equipment was not required where there was a reasonable probability of injury that could be prevented by such equipment:    a) Perry Fiberglass Products, Inc., Avon Lake, Ohio:  On or about February 13, 2014, the employer did not ensure that employees who dispensed hazardous chemicals into secondary containers wore appropriate eye protection when doing so.  Employees were exposed to eye injuries from splashing corrosive chemicals.
Recent events (2)
  • — I (S) $2310
  • — Z (S) $4620

1910.157 C01

Serious Gravity 5 1 instance 6 exposed
Issued
Jul 23, 2014
Penalty
Initial $3,080 · Current $1,540 Reduced
29 CFR 1910.157(c)(1): Portable fire extinguishers were not mounted, located and identified so that they were readily accessible without subjecting the employees to injuries:    a) Perry Fiberglass Products, Inc., Avon Lake, Ohio:  On or about February 13, 2014, the employer did not ensure that unobstructed access to each fire extinguisher was maintained, exposing employee to slip, trip and fall hazards.
Recent events (2)
  • — I (S) $1540
  • — Z (S) $3080

1910.157 G01

Serious Gravity 5 1 instance 68 exposed
Issued
Jul 23, 2014
Abate by
Aug 8, 2014
Penalty
Initial $3,850 · Current $1,925 Reduced
29 CFR 1910.157(g)(1): An educational program was not provided for all employees to familiarize them with the general principles of fire extinguisher use and the hazards involved with incipient stage fire fighting:     a)  Perry Fiberglass Products, Inc., Avon Lake, Ohio:  On or about July 2, 2014, the employer did not ensure that employees were provided with a training program to familiarize them with the general principles of fire extinguisher use and the hazards involved with incipient stage firefighting, exposing them to burn hazards.  The employer expected employees use fire extinguishers in the event of a fire.
Recent events (2)
  • — I (S) $1925
  • — Z (S) $3850

1910.106 E02 IV D

Repeat Gravity 5 1 instance 6 exposed
Issued
Jul 23, 2014
Penalty
Initial $7,700 · Current $3,850 Reduced
29 CFR 1910.106(e)(2)(iv)(d): Flammable liquids were not drawn from or transferred into vessels, containers, or portable tanks within a building only through a closed piping system, from safety cans, by means of a device drawing through the top, or from a container or portable tanks by gravity through an approved self-closing valve:    a)  Perry Fiberglass Products, Inc., Avon Lake, Ohio:  On or about February 13, 2014, the employer did not ensure that a 275 gallon portable tank of Category 3 CORVE8401 resin, located in the welding area of building #2, was equipped with an approved self-closing valve.    Perry Fiberglass Products, Inc. was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1910.106(e)(2)(iv)(d), which was contained in OSHA Inspection Number 313781320, citation number 1, item number 1 and was affirmed as a final order on July 21, 2010, with respect to a workplace located at 33660 Pin Oak Parkway, Avon Lake, Ohio.
Recent events (2)
  • — I (R) $3850
  • — Z (R) $7700

1910.106 E06 II

Repeat Gravity 5 1 instance 6 exposed
Issued
Jul 23, 2014
Penalty
Initial $7,700 · Current $3,850 Reduced
29 CFR 1910.106(e)(6)(ii): Category 1 or 2 flammable liquids, or Category 3 flammable liquids with a flashpoint below 100 °F (37.8 °C), were dispensed into containers without the nozzle and container being electrically interconnected:    a)  Perry Fiberglass Products, Inc., Avon Lake, Ohio:  On or about February 13, 2014, the employer did not ensure that a 275 gallon portable tank of Category 3 CORVE8401 resin, located in the welding area of building #2, was equipped with a bonding system to electrically interconnect the dispensing faucet and the plastics buckets used to transfer product to the welding area nearby.    Perry Fiberglass Products, Inc. was previously cited for a violation of this occupational safety and health standard or its equivalent standard 29 CFR 1910.106(e)(6)(i), which was contained in OSHA Inspection Number 313781320, citation number 1, item number 2 and was affirmed as a final order on July 21, 2010, with respect to a workplace located at 33660 Pin Oak Parkway, Avon Lake, Ohio.
Recent events (2)
  • — I (R) $3850
  • — Z (R) $7700

1910.132 D02

Other-than-serious 1 instance 68 exposed
Issued
Jul 23, 2014
Abate by
Aug 1, 2014
Penalty
Initial $0 · Current $0
29 CFR 1910.132(d)(2): The employer did not verify, through a written certification, that the required workplace hazard assessment had been performed:  a) Perry Fiberglass Products, Inc., Avon Lake, Ohio:  On or about February 13, 2014, the employer did not certify that a hazard assessment was performed to address the physical and health hazards found in the workplace and to determine whether the use or what type of personal protective equipment was necessary.
Recent events (2)
  • — I (O) $0
  • — Z (O) $0

View Perry Fiberglass Products, INC.'s full OSHA safety record →